STM 123 No 21 Pty Ltd v Woollahra Municipal Council [2019] NSWLEC 1574

STM 123 No 21 Pty Ltd v Woollahra Municipal Council [2019] NSWLEC 1574

The Court upheld the appeal and approved the amended development application, finding that the parties' agreement satisfied the statutory requirements, the site benefited from existing use rights, and all relevant statutory considerations had been addressed.

Jurisdiction
Australia
Judgment Date
27 November 2019
Procedural Posture
Appeal / Final Determination at Conciliation Conference
Outcome
Appeal upheld; development application approved subject to conditions; applicant to pay respondent's costs resulting from amendment
Legal Topics
['development Application' 'existing Use Rights' 'conciliation Conference' 'amendment of Application' 'costs']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Appeal / Final Determination at Conciliation Conference

  1. 1 ['Whether the applicant is entitled to amend the development application' 'Whether the development application should be approved subject to conditions' 'Whether existing use rights are present for a residential flat building']

Ratio Decidendi

The Court upheld the appeal and approved the amended development application, finding that the parties' agreement satisfied the statutory requirements, the site benefited from existing use rights, and all relevant statutory considerations had been addressed.

Court Disposition

Appeal upheld; development application approved subject to conditions; applicant to pay respondent's costs resulting from amendment

Orders

  • ['Applicant given leave to amend the development application and rely on plans as per Condition A.3 of Annexure "A".' "Applicant to pay respondent's costs thrown away as a result of amending the application, pursuant to section 8.15(3) of the Environmental Planning and Assessment Act 1979 as agreed or assessed."...