Stucoid Pty Ltd v Stadiums Pty Ltd [1960] HCA 41
Time limits in ss. 9, 10, and 19 of the Contractors' and Workmen's Lien Acts commence upon completion of the work under the relevant subcontract; as Stucoid Pty Ltd gave notice and commenced proceedings after these periods expired, no lien or charge attached or was enforceable and the appeals must be dismissed.
Source-derived case information.
- Jurisdiction
- Australia
- Procedural Posture
- Appeal / Final Judgment on Appeal
- Outcome
- Appeals dismissed with costs.
- Legal Topics
- ["contractors' and Workmen's Lien Acts (qld)" "time Limits for Enforcing Mechanic's Liens" 'construction and Application of Statutory Liens and Charges']
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Appeal / Final Judgment on Appeal
Legal Issues
- 1 ["Whether the time limitation for claiming under ss. 9, 10, and 19 of the Contractors' and Workmen's Lien Acts runs from completion of the work under the subcontract or the head contract" "Whether Stucoid Pty Ltd's notices and proceedings were within time as required by the relevant statutory provisions"]
Ratio Decidendi
Time limits in ss. 9, 10, and 19 of the Contractors' and Workmen's Lien Acts commence upon completion of the work under the relevant subcontract; as Stucoid Pty Ltd gave notice and commenced proceedings after these periods expired, no lien or charge attached or was enforceable and the appeals must be dismissed.
Court Disposition
Appeals dismissed with costs.
Orders
- ['Appeals dismissed with costs.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment