Boulos v Campbelltown City Council [2022] NSWLEC 1625

Boulos v Campbelltown City Council [2022] NSWLEC 1625

The Court upheld the appeal and granted development consent as all jurisdictional and statutory prerequisites were met, the amended application met relevant planning, environmental, and character compatibility requirements, and the parties' agreement reflected a decision the Court could properly make under the relevant legislation.

Jurisdiction
Australia
Judgment Date
11 November 2022
Procedural Posture
Class 1 Appeal / Post Conciliation Conference, Determination on Consent Orders
Outcome
Appeal upheld; development consent granted subject to conditions; costs order against Applicant.
Legal Topics
['development Application' 'boarding House' 'land Use Zoning' 'conciliation Conference' 'development Consent' 'local Environmental Plan' 'state Environmental Planning Policies']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Class 1 Appeal / Post Conciliation Conference, Determination on Consent Orders

  1. 1 ['Whether development consent should be granted for a boarding house in R2 Low Density Residential zone under the amended application' 'Whether the development complies with relevant planning instruments including the Campbelltown Local Environmental Plan 2015 and various State Environmental Planning Policies' 'Whether the required jurisdictional and statutory prerequisites for granting consent have been satisfied' 'Whether stormwater and flood planning requirements are met']

Ratio Decidendi

The Court upheld the appeal and granted development consent as all jurisdictional and statutory prerequisites were met, the amended application met relevant planning, environmental, and character compatibility requirements, and the parties' agreement reflected a decision the Court could properly make under the relevant legislation.

Court Disposition

Appeal upheld; development consent granted subject to conditions; costs order against Applicant.

Orders

  • ["The Applicant is to pay the Respondent's costs thrown away, by reason of the amendment of Development Application No. 1038/2021/DA-BH, in the agreed sum of $14,000 within 28 days." 'The Appeal is upheld.' "Development consent is granted to Development Application No. 1038/2021/DA-BH for the demolition of the...