Telco Select Pty Ltd v Tweed Shire Council [2006] NSWLEC 638

Telco Select Pty Ltd v Tweed Shire Council [2006] NSWLEC 638

The amended proposal, with a further 200 mm height reduction and 1 m increased setback from Hungerford Lane, satisfied the objectives and performance criteria of the relevant planning controls despite non-compliance with numeric standards. The limited height non-compliance was justified under SEPP 1 because the development respected the topography, achieved acceptable view sharing, did not cause undue view loss or streetscape impact, provided satisfactory traffic and access arrangements, and produced a good urban design outcome consistent with the medium density residential zoning.

Jurisdiction
Australia
Judgment Date
28 April 2006
Procedural Posture
Appeal Under S 97 of the Environmental Planning and Assessment Act Concerning a Development Application / Extempore Judgment on Consent Orders
Outcome
Appeal upheld by consent; SEPP 1 objection allowed; deferred commencement consent granted subject to conditions.
Legal Topics
['integrated Development of Six Dwellings' 'floor Space Ratio' 'height Variation' 'state Environmental Planning Policy No. 1 Objection' 'view Sharing' 'traffic and Parking' 'character of Area' 'deferred Commencement Consent']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Appeal Under S 97 of the Environmental Planning and Assessment Act Concerning a Development Application / Extempore Judgment on Consent Orders

  1. 1 ['Whether the amended development application for six integrated dwellings should be approved by deferred commencement consent.' 'Whether the SEPP 1 objection to vary the 2-storey height limitation in cl 16 of the Tweed LEP 2000 should be allowed.' 'Whether the proposed development achieved acceptable view sharing and view corridors.' 'Whether traffic, parking and access arrangements, including Hungerford Lane and the pedestrian access path, warranted refusal.' 'Whether the proposed development was compatible with the applicable planning controls and the character of the Kingscliff Hill area.']

Ratio Decidendi

The amended proposal, with a further 200 mm height reduction and 1 m increased setback from Hungerford Lane, satisfied the objectives and performance criteria of the relevant planning controls despite non-compliance with numeric standards. The limited height non-compliance was justified under SEPP 1 because the development respected the topography, achieved acceptable view sharing, did not cause undue view loss or streetscape impact, provided satisfactory traffic and access arrangements, and produced a good urban design outcome consistent with the medium density residential zoning.

Court Disposition

Appeal upheld by consent; SEPP 1 objection allowed; deferred commencement consent granted subject to conditions.

Orders

  • ['The appeal in respect of the property known as both 17-19 Moss Street and 16-18 Hungerford Lane, Kingscliffe, is upheld by consent.' 'The SEPP 1 objection to vary the 2-storey height limitation contained in cl 16 of the Tweed LEP 2000 is allowed.' "The development application submitted to Tweed Shire Council and...