The Owners Strata Plan No 57164 v Yau [2016] NSWSC 1056

The Owners Strata Plan No 57164 v Yau [2016] NSWSC 1056

The EC had the authority to instruct counsel to settle the proceedings; the failure to comply with the notice requirements of Sch 3 cl 6 did not invalidate the EC's decision. The settlement agreement was made with actual authority. Alternatively, the conduct of the Owners Corporation after the agreement amounted to...

Source-derived case information.

Parties
Plaintiff: The Owners Strata Plan No 57164; Defendant: Annie May Fun Yau; Defendant: Andy Sung Kit Yau
Jurisdiction
Australia
Judgment Date
02 August 2016
Procedural Posture
Civil / Judgment After Hearing
Outcome
Amended Statement of Claim is dismissed with costs.
Legal Topics
Strata Title—management and Control, Authority of Agents in Contracts, Setting Aside Consent Orders, Notice Requirements for Meetings Under Strata Schemes Management Act 1996 (nsw)
Real Property Contracts Civil Procedure Strata Title—management and Control Authority of Agents in Contracts Setting Aside Consent Orders Notice Requirements for Meetings Under Strata Schemes Management Act 1996 (nsw)

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 17 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

The Owners Strata Plan No 57164

Plaintiff

Annie May Fun Yau

Defendant

Andy Sung Kit Yau

Defendant

Procedural Posture

Civil / Judgment After Hearing

  1. 1 Whether the EC meeting was invalid due to failure to give notice as required by Strata Schemes Management Act 1996 (NSW), Sch 3, cl 6
  2. 2 Whether the EC lacked authority to instruct settlement due to subject matter of the agreement
  3. 3 Whether counsel had actual, implied or ostensible authority to bind the Owners Corporation

Ratio Decidendi

The EC had the authority to instruct counsel to settle the proceedings; the failure to comply with the notice requirements of Sch 3 cl 6 did not invalidate the EC's decision. The settlement agreement was made with actual authority. Alternatively, the conduct of the Owners Corporation after the agreement amounted to ratification. There was no basis to set aside the consent orders, and the plaintiff's Amended Statement of Claim was dismissed with costs.

Court Disposition

Amended Statement of Claim is dismissed with costs.

Orders

  • Amended Statement of Claim dismissed with costs.