The Owners – Strata Plan No 85305 v Dyldam Developments Pty Ltd [2019] NSWCATCD 73
The first and second interim occupation certificates should not have been issued because development consent preconditions required before issue had not been complied with, contrary to s109H(2) of the Environmental Planning and Assessment Act 1979. The reference to an occupation certificate in s3C(2) of the Home Building Act 1989 applies only to an occupation certificate valid under the EPA Act. Accordingly, completion occurred on 12 October 2011 when the third occupation certificate issued, and proceedings commenced on 4 October 2018 were within the 7 year period in s18E(1).
- Jurisdiction
- Australia
- Judgment Date
- 05 March 2019
- Procedural Posture
- Home Building Statutory Warranty Proceedings / Preliminary Hearing on Jurisdiction/time to Commence Proceedings
- Outcome
- Dyldam Developments Pty Ltd's application that the proceedings were brought out of time was dismissed.
- Legal Topics
- ['time to Commence Proceedings' 'statutory Warranties' 'occupation Certificates' 'validity of Interim Occupation Certificate']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Home Building Statutory Warranty Proceedings / Preliminary Hearing on Jurisdiction/time to Commence Proceedings
Legal Issues
- 1 ['Whether the proceedings were commenced outside the time stipulated in s18E of the Home Building Act 1989.' 'Whether the first or second interim occupation certificate authorised occupation and use of the whole building for the purposes of s3C(2) of the Home Building Act 1989 despite unmet development consent preconditions.' 'Whether the building work was completed on 5 September 2011, 9 September 2011, or 12 October 2011 for limitation purposes.']
Ratio Decidendi
The first and second interim occupation certificates should not have been issued because development consent preconditions required before issue had not been complied with, contrary to s109H(2) of the Environmental Planning and Assessment Act 1979. The reference to an occupation certificate in s3C(2) of the Home Building Act 1989 applies only to an occupation certificate valid under the EPA Act. Accordingly, completion occurred on 12 October 2011 when the third occupation certificate issued, and proceedings commenced on 4 October 2018 were within the 7 year period in s18E(1).
Court Disposition
Dyldam Developments Pty Ltd's application that the proceedings were brought out of time was dismissed.
Orders
- ["Dyldam Developments Pty Ltd's application for an order that the time limit for The Owners – Strata Plan No 85305 to have commenced these proceedings expired on 5 September 2018 with the result that the proceedings have been brought out of time is dismissed." 'Any costs application associated with this application...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment