Visscher v BHP Petroleum Pty Limited re the ship "Griffin Venture" [2002] NSWSC 315
Because the plaintiff was relevantly an employee at the time of the alleged services and was carrying out obligations for which he was rewarded, the proposed restitutionary claim had no prospect of success. Leave to amend was refused. The court also answered that the salvage claim was not maintainable due to limitation and time should not be extended, and dismissed the claim.
- Jurisdiction
- Australia
- Judgment Date
- 07 March 2002
- Procedural Posture
- Admiralty Claim for Salvage and Application to Amend Statement of Claim to Add a Claim in Restitution / Judgment on Application to Amend and Answers to Separate Questions
- Outcome
- Plaintiff's application to amend refused; claim dismissed; plaintiff ordered to pay the defendant's costs.
- Legal Topics
- ['salvage Claim' 'volunteer or Employee Status' 'unjust Enrichment' 'amendment of Statement of Claim' 'statute Barred Claim']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Admiralty Claim for Salvage and Application to Amend Statement of Claim to Add a Claim in Restitution / Judgment on Application to Amend and Answers to Separate Questions
Legal Issues
- 1 ["Whether the plaintiff's salvage claim was not maintainable because proceedings were commenced after the applicable limitation period." "Whether time for commencement of the plaintiff's salvage claim should be extended." 'By whom the plaintiff was employed on 29 May 1994.' 'Whether the plaintiff was a volunteer or an employee in respect of the services alleged to have been rendered to the Griffin Venture.' 'Whether the plaintiff should have leave to amend the statement of claim to add a restitutionary claim.']
Ratio Decidendi
Because the plaintiff was relevantly an employee at the time of the alleged services and was carrying out obligations for which he was rewarded, the proposed restitutionary claim had no prospect of success. Leave to amend was refused. The court also answered that the salvage claim was not maintainable due to limitation and time should not be extended, and dismissed the claim.
Court Disposition
Plaintiff's application to amend refused; claim dismissed; plaintiff ordered to pay the defendant's costs.
Orders
- ["I refuse the plaintiff's application to amend the statement of claim." 'I dismiss the claim.' "I order the plaintiff to pay the defendant's costs."]
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment