SafeWork NSW v TJN Construction Group Pty Ltd [2024] NSWDC 563
The defendant, as a principal contractor and PCBU, failed in its non-delegable statutory duty to ensure, so far as was reasonably practicable, the health and safety of its workers by not conducting a risk assessment, not implementing adequate control measures and supervision, and not providing appropriate PPE, training, or emergency resources, thereby exposing workers to an obvious risk of serious injury. The objective seriousness was high, mitigation steps were straightforward, the actual injuries were grave, and general and specific deterrence require a substantial penalty, moderated for plea and capacity to pay.
- Parties
- Prosecutor: SafeWork NSW; Defendant: TJN Construction Group Pty Ltd
- Jurisdiction
- Australia
- Judgment Date
- 28 November 2024
- Procedural Posture
- Criminal / Sentence
- Outcome
- Convicted and fined; costs ordered
- Legal Topics
- Prosecution, Work Health and Safety, Duty of Persons Undertaking Business, Risk of Death or Serious Injury, Recklessness, Sentence, Objective Seriousness, Mitigating Factors, Aggravating Factors, Plea of Guilty, Appropriate Discount, General Deterrence, Specific Deterrence, Remorse and Contrition, Parity, Maximum Penalties, Capacity to Pay, Costs
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
SafeWork NSW
Prosecutor
TJN Construction Group Pty Ltd
Defendant
Procedural Posture
Criminal / Sentence
Legal Issues
- 1 Whether the defendant breached its health and safety duty under s 19(1) of the Work Health and Safety Act 2011 (NSW) resulting in exposure of workers to risk of serious injury
- 2 What is the appropriate sentence considering objective seriousness, aggravating and mitigating factors, parity, capacity to pay, and other sentencing principles
Ratio Decidendi
The defendant, as a principal contractor and PCBU, failed in its non-delegable statutory duty to ensure, so far as was reasonably practicable, the health and safety of its workers by not conducting a risk assessment, not implementing adequate control measures and supervision, and not providing appropriate PPE, training, or emergency resources, thereby exposing workers to an obvious risk of serious injury. The objective seriousness was high, mitigation steps were straightforward, the actual injuries were grave, and general and specific deterrence require a substantial penalty, moderated for plea and capacity to pay.
Court Disposition
Convicted and fined; costs ordered
Orders
- The defendant is convicted.
- The appropriate fine for the offence is $400,000 and reduced by 25% to reflect the plea of guilty, leaving a fine of $300,000.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment