Tyco Australia Pty. Ltd. v. Optus Networks Pty. Ltd. & Ors. [2004] NSWCA 333

Tyco Australia Pty. Ltd. v. Optus Networks Pty. Ltd. & Ors. [2004] NSWCA 333

Optus' damages for equipment were to be reduced not just by the second-hand value of leftover equipment but, for certain items, by their full cost on the basis that Optus would have had to acquire them regardless of Tyco's breach, due to their actual use. Costs spent upgrading Blacktown data centre were held to confer a benefit on Optus (freeing up Rosebery), and thus the full expenditure should be deducted from damages. Business recovery savings were collateral and not to be deducted. The Bullock order was set aside for lack of evidential basis that Tyco induced Optus to pursue NDY. The cross-appeal on interest failed since no error was shown in the selected date for pre-judgment interest.

Jurisdiction
Australia
Judgment Date
20 September 2004
Procedural Posture
Appeal / Judgment
Outcome
Appeal allowed in part; cross-appeal dismissed.
Legal Topics
['measure of Damages' 'mitigation' 'betterment' 'deduction for Benefits' 'onus of Proof' 'interest on Damages' 'costs (bullock Order)']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Appeal / Judgment

  1. 1 ['Whether Optus was entitled to the full cost of replacing/cleaning equipment after the incident or if deductions were required for benefits received (e.g. additional equipment left over, upgraded data center).' 'Whether benefits received by Optus (e.g. freed up data center, cancellation of business recovery contracts) were collateral or had to be deducted from damages.' 'Appropriate quantification and deductions from awarded damages for equipment, upgrade expenditures, and business recovery savings.' 'Appropriate award of interest and whether pre-judgment interest should run from a particular date.' 'Appropriateness of the Bullock order for costs against Tyco (and Leighton) in respect of costs payable to NDY.']

Ratio Decidendi

Optus' damages for equipment were to be reduced not just by the second-hand value of leftover equipment but, for certain items, by their full cost on the basis that Optus would have had to acquire them regardless of Tyco's breach, due to their actual use. Costs spent upgrading Blacktown data centre were held to confer a benefit on Optus (freeing up Rosebery), and thus the full expenditure should be deducted from damages. Business recovery savings were collateral and not to be deducted. The Bullock order was set aside for lack of evidential basis that Tyco induced Optus to pursue NDY. The cross-appeal on interest failed since no error was shown in the selected date for pre-judgment interest.

Court Disposition

Appeal allowed in part; cross-appeal dismissed.

Orders

  • ['Damages to Optus to be reduced by the cost of certain equipment found to have been required regardless of the incident; deduction for the Blacktown upgrade costs; order for costs (Bullock order) against Tyco and Leighton set aside; cross-appeal on interest dismissed; parties to bring in short minutes for final...