Unity Link (Vic) Pty Ltd v Cumberland Council [2018] NSWLEC 1349
The parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979, and the Commissioner was satisfied the Court could make the decision, therefore the appeal is upheld and the development application is approved subject to conditions.
- Parties
- Applicant: Unity Link (Vic) Pty Ltd; Respondent: Cumberland Council
- Jurisdiction
- Australia
- Judgment Date
- 09 July 2018
- Procedural Posture
- Development Application Appeal / Final Orders After Conciliation Conference
- Outcome
- Appeal upheld. Development application approved subject to conditions.
- Legal Topics
- Development Application, Conciliation Conference, Section 34 Agreement
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Unity Link (Vic) Pty Ltd
Applicant
Cumberland Council
Respondent
Procedural Posture
Development Application Appeal / Final Orders After Conciliation Conference
Legal Issues
- 1 Whether development application DA 454/2017 should be approved
- 2 Whether the agreement reached at conciliation satisfies s 34(3) Land and Environment Court Act 1979
Ratio Decidendi
The parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979, and the Commissioner was satisfied the Court could make the decision, therefore the appeal is upheld and the development application is approved subject to conditions.
Court Disposition
Appeal upheld. Development application approved subject to conditions.
Orders
- The Applicant is given leave to amend the development application and rely upon specified plans.
- The appeal is upheld.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment