Universal Property Group Pty Ltd v Blacktown City Council [2021] NSWLEC 1183

Universal Property Group Pty Ltd v Blacktown City Council [2021] NSWLEC 1183

The jurisdictional prerequisites for development consent, including permissible use, minimum density, contamination, infrastructure, design quality, sustainability, and notification requirements, have been satisfied. The proposed development complies with relevant planning instruments and no public or agency objections remain. Under s 34(3) of the Land and Environment Court Act 1979, the Court must grant consent in accordance with the agreement reached by the parties at the conciliation conference. The appeal is upheld and development consent is granted subject to agreed conditions and documentation.

Jurisdiction
Australia
Judgment Date
15 April 2021
Procedural Posture
Development Appeal / Final Orders After Conciliation Conference
Outcome
Appeal upheld; development consent granted subject to conditions.
Legal Topics
['development Consent' 'apartment Design' 'drainage' 'zoning' 'contamination' 'notification Requirements' 'basix Certification' 'subdivision']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Development Appeal / Final Orders After Conciliation Conference

  1. 1 ['Whether the proposed residential flat building should be granted development consent under relevant planning instruments' 'Whether the jurisdictional prerequisites for consent are satisfied under the Environmental Planning and Assessment Act 1979 and other applicable policies' 'Whether the design, density, infrastructure, contamination, notification, and sustainability requirements are met']

Ratio Decidendi

The jurisdictional prerequisites for development consent, including permissible use, minimum density, contamination, infrastructure, design quality, sustainability, and notification requirements, have been satisfied. The proposed development complies with relevant planning instruments and no public or agency objections remain. Under s 34(3) of the Land and Environment Court Act 1979, the Court must grant consent in accordance with the agreement reached by the parties at the conciliation conference. The appeal is upheld and development consent is granted subject to agreed conditions and documentation.

Court Disposition

Appeal upheld; development consent granted subject to conditions.

Orders

  • ['Applicant granted leave to amend the development application to rely on specified amended plans and documents.' "Applicant to pay respondent's costs as agreed or assessed." 'Development Application No. DA-19-01486 for construction of a residential flat building (containing 144 units), basement car parking,...