Urban Peninsula Pty Limited v Ku-ring-gai Council [2013] NSWLEC 1030
It was reasonable and appropriate to impose the council's proposed condition limiting the use of the tunnel solely to vehicular access for Dev 2, requiring arrangements and easements before use, and imposing a 7-year period after which the tunnel must be removed if Dev 2 had not proceeded. This satisfied the planning purpose, directly related to the proposed development, and was not unreasonable. Conditional consent was therefore granted subject to conditions.
- Parties
- Applicant: Urban Peninsula Pty Limited; Respondent: Ku-ring-gai Council
- Jurisdiction
- Australia
- Judgment Date
- 22 February 2013
- Procedural Posture
- Development Appeal / Decision on Appeal From Refusal of Development Application
- Outcome
- Appeal upheld
- Legal Topics
- Development Application, Conditions of Consent, Easements, Plan of Management, Orderly Development
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Urban Peninsula Pty Limited
Applicant
Ku-ring-gai Council
Respondent
Procedural Posture
Development Appeal / Decision on Appeal From Refusal of Development Application
Legal Issues
- 1 Whether conditions regarding plan of management and easements for access to basement tunnel are valid, reasonable and appropriate for the development application
- 2 Whether the proposed tunnel satisfies principles of orderly and economic use of land
Ratio Decidendi
It was reasonable and appropriate to impose the council's proposed condition limiting the use of the tunnel solely to vehicular access for Dev 2, requiring arrangements and easements before use, and imposing a 7-year period after which the tunnel must be removed if Dev 2 had not proceeded. This satisfied the planning purpose, directly related to the proposed development, and was not unreasonable. Conditional consent was therefore granted subject to conditions.
Court Disposition
Appeal upheld
Orders
- The appeal is upheld.
- Development consent is granted to DA 0099/12 for construction of a basement level driveway (tunnel) between 2-6 Buckingham and 6A-8 Buckingham Road, Killara, subject to the conditions in Annexure A.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment