Vigor Master Pty Ltd v Ku-ring-gai Council [2018] NSWLEC 1026

Vigor Master Pty Ltd v Ku-ring-gai Council [2018] NSWLEC 1026

The matter was disposed of in accordance with an agreement under s 34(3) of the Land and Environment Court Act 1979; as the Court was satisfied the decision was one it could have made, it was required to dispose of the proceedings accordingly.

Parties
Applicant: Vigor Master Pty Ltd; Respondent: Ku-ring-gai Council
Jurisdiction
Australia
Judgment Date
23 January 2018
Procedural Posture
Appeal / Conciliation Conference and Final Orders
Outcome
Appeal upheld
Legal Topics
Modification Application, Deferred Commencement Condition, Conciliation Conference, S 34(3) Land and Environment Court Act 1979

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Vigor Master Pty Ltd

Applicant

Ku-ring-gai Council

Respondent

Procedural Posture

Appeal / Conciliation Conference and Final Orders

  1. 1 Whether the deferred commencement condition in the development consent should be removed

Ratio Decidendi

The matter was disposed of in accordance with an agreement under s 34(3) of the Land and Environment Court Act 1979; as the Court was satisfied the decision was one it could have made, it was required to dispose of the proceedings accordingly.

Court Disposition

Appeal upheld

Orders

  • The appeal is upheld.
  • Application No. MOD0211/16 to delete the deferred commencement condition of DA 0255/16 is approved and the development consent is now subject to the conditions annexed and marked 'A'.