White Constructions Pty Ltd v Donaldson & Anor [2006] NSWSC 749
There is a serious issue to be determined as to the proper construction of the contractual documents and the bank guarantee; the status quo should be maintained and an injunction granted restraining any further call on the guarantee pending resolution.
- Jurisdiction
- Australia
- Judgment Date
- 13 July 2006
- Procedural Posture
- Injunction Application / Interlocutory/ex Tempore Judgment
- Outcome
- Injunction granted with costs to the plaintiff
- Legal Topics
- ['construction and Interpretation of Contract' 'injunctions' 'trusts' 'performance Guarantee']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Injunction Application / Interlocutory/ex Tempore Judgment
Legal Issues
- 1 ['Whether the notice calling on the bank guarantee was void and of no effect' 'Whether there is a serious issue to be tried regarding construction of the agreement and guarantees' 'Whether an injunction should issue to restrain breach of negative stipulation']
Ratio Decidendi
There is a serious issue to be determined as to the proper construction of the contractual documents and the bank guarantee; the status quo should be maintained and an injunction granted restraining any further call on the guarantee pending resolution.
Court Disposition
Injunction granted with costs to the plaintiff
Orders
- ['Orders in terms of paragraphs 4 to 7 of the summons until further order' 'First defendant restrained from taking any further step to obtain the guarantee moneys until further order' "Defendant to pay the plaintiff's costs of the motion"]
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment