White Constructions Pty Ltd v PBS Holdings Pty Ltd [2019] NSWSC 1166
The plaintiff did not establish that the defendants breached their contractual obligations, nor that any losses claimed were caused by the alleged delay in sewer design approval; the weight of evidence pointed to the plaintiff's own instructions causing any delay, and no relevant damages were established.
- Jurisdiction
- Australia
- Judgment Date
- 06 September 2019
- Procedural Posture
- Principal Judgment / Final Decision After Trial
- Outcome
- Proceedings dismissed
- Legal Topics
- ['damages for Delay' 'contractual Breach' 'privity of Contract' 'programming/delay Analysis' 'causation in Damages']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Principal Judgment / Final Decision After Trial
Legal Issues
- 1 ['Whether the defendants breached contractual obligations to prepare an acceptable sewer design within a reasonable time' 'Whether loss and damage claimed by the plaintiff were established and causally linked to any breach' 'Appropriate method of delay analysis and whether delay in sewer design approval delayed completion of the project']
Ratio Decidendi
The plaintiff did not establish that the defendants breached their contractual obligations, nor that any losses claimed were caused by the alleged delay in sewer design approval; the weight of evidence pointed to the plaintiff's own instructions causing any delay, and no relevant damages were established.
Court Disposition
Proceedings dismissed
Orders
- ["Plaintiff's claim is dismissed" 'Plaintiff to pay the costs of the first and second defendants unless an alternative costs order is sought within seven days' 'Exhibits to be returned']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment