Su v Winning Builders Pty Ltd [2024] NSWCATCD 44
The Tribunal determined a work order was appropriate in the circumstances considering the builder's breaches and the relational breakdown, requiring rectification by a licensed third-party contractor with specified terms and inspector oversight. No direction would be included to move structural columns because, despite breach, rectification would be disproportionate. Delay damages for alternative accommodation were awarded, calculated to the date builder lost access to the site, as the loss was within contemplation of the parties at contract formation. Claims for contract price adjustment were rejected, the contract being fixed price and no written variation established.
- Parties
- First Applicant: Jian Yu Su; Second Applicant: Bao Ling Zhao; Respondent: Winning Builders Pty Ltd
- Jurisdiction
- Australia
- Judgment Date
- 13 June 2024
- Procedural Posture
- Civil Building Dispute / Final Decision and Orders
- Outcome
- Orders for rectification works by third party contractor and payment of delay damages to applicants; no order for contract price adjustment; directions for parties to apply for costs.
- Legal Topics
- Statutory Warranties, Work Orders, Delay Damages, Rectification of Defects, Extensions of Time, Oral Variation, Contract Interpretation, Remoteness of Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Jian Yu Su
First Applicant
Bao Ling Zhao
Second Applicant
Winning Builders Pty Ltd
Respondent
Procedural Posture
Civil Building Dispute / Final Decision and Orders
Legal Issues
- 1 Whether Tribunal has discretion and jurisdiction to make a works order under s 48O(1)(c) Home Building Act 1989 NSW while the contract is on foot; Whether a work order should require a third party contractor, include direction to move structural columns, or cover incomplete and defective works; Whether applicants are entitled to delay damages; Whether applicants are entitled to a contract price adjustment; Whether various alleged oral variations to contract are established
Ratio Decidendi
The Tribunal determined a work order was appropriate in the circumstances considering the builder's breaches and the relational breakdown, requiring rectification by a licensed third-party contractor with specified terms and inspector oversight. No direction would be included to move structural columns because, despite breach, rectification would be disproportionate. Delay damages for alternative accommodation were awarded, calculated to the date builder lost access to the site, as the loss was within contemplation of the parties at contract formation. Claims for contract price adjustment were rejected, the contract being fixed price and no written variation established.
Court Disposition
Orders for rectification works by third party contractor and payment of delay damages to applicants; no order for contract price adjustment; directions for parties to apply for costs.
Orders
- Within 28 days, respondent to pay applicants $15,342.16.
- Work order made under s 48O(1)(c) Home Building Act 1989 for rectification works via licensed third party in terms set out in para [191] of Reasons, with inspector oversight and detailed conditions in annexures.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment