Aldred & anor v Woollahra Municipal Council [2015] NSWLEC 1467

Aldred & anor v Woollahra Municipal Council [2015] NSWLEC 1467

The agreement reached between the parties at a conciliation conference was acceptable to the Court and satisfied s 34(3) Land and Environment Court Act 1979, requiring orders to be made giving effect to the agreement.

Parties
Applicants: Russell John Aldred and Michael John Aldred; Respondent: Woollahra Municipal Council
Jurisdiction
Australia
Judgment Date
18 November 2015
Procedural Posture
Development Application, Class 1 / Conciliation Conference and Final Orders After Agreement
Outcome
Proceedings disposed of in accordance with parties' agreement under s 34(3) Land and Environment Court Act 1979
Legal Topics
Tree Removal, Impact on Views, Conciliation Conference, Agreed Orders

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 1
Sign in to unlock

Parties

Russell John Aldred and Michael John Aldred

Applicants

Woollahra Municipal Council

Respondent

Procedural Posture

Development Application, Class 1 / Conciliation Conference and Final Orders After Agreement

  1. 1 Whether the parties' agreement as to tree removal and related impacts is acceptable under s 34(3) of the Land and Environment Court Act 1979

Ratio Decidendi

The agreement reached between the parties at a conciliation conference was acceptable to the Court and satisfied s 34(3) Land and Environment Court Act 1979, requiring orders to be made giving effect to the agreement.

Court Disposition

Proceedings disposed of in accordance with parties' agreement under s 34(3) Land and Environment Court Act 1979

Orders

  • Final orders made on 18 November 2015 giving effect to parties' agreement