Hymak Pty Ltd & Anor v Wyong Shire Council [2015] NSWLEC 1546

Hymak Pty Ltd & Anor v Wyong Shire Council [2015] NSWLEC 1546

The Court disposed of the proceedings by making orders reflecting the agreement reached between the parties at conciliation conference in accordance with s 34(3) Land and Environment Court Act 1979, being satisfied such decision was within the Court's power.

Jurisdiction
Australia
Judgment Date
21 December 2015
Procedural Posture
Class 1 / Orders Following Conciliation Conference
Outcome
Orders by agreement under s 34(3) Land and Environment Court Act 1979; proceedings disposed of in accordance with parties' agreement
Legal Topics
['subdivision' 'conciliation Conference' 'agreement Between Parties' 'orders Under S 34(3) Land and Environment Court Act 1979']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Class 1 / Orders Following Conciliation Conference

  1. 1 ['Whether agreement reached at conciliation conference is one the Court could have made in proper exercise of its functions under s 34(3) Land and Environment Court Act 1979']

Ratio Decidendi

The Court disposed of the proceedings by making orders reflecting the agreement reached between the parties at conciliation conference in accordance with s 34(3) Land and Environment Court Act 1979, being satisfied such decision was within the Court's power.

Court Disposition

Orders by agreement under s 34(3) Land and Environment Court Act 1979; proceedings disposed of in accordance with parties' agreement

Orders

  • ['Final orders made to give effect to the agreement between the parties as set out in writing']