Zebicon Pty Ltd v Remo Constructions Pty Ltd [2008] NSWSC 1408
Payment claim 11 was served on Remo on 19 July 2008 because the evidence of Mr Zerilli and the fax transmission report marked OK supported an unrebutted inference that the claim was transmitted to and received into the memory of Remo's fax machine at its ordinary place of business. Receipt did not require printing out or attention by Remo staff, and service by facsimile under s 31(1)(c) was not confined to normal office hours. The Court was not satisfied that Remo gave a payment schedule to Mr Zerilli on 4 August 2008. Zebicon was therefore entitled to judgment.
- Jurisdiction
- Australia
- Judgment Date
- 24 December 2008
- Procedural Posture
- Building and Construction Payment Claim Dispute / Preliminary Decision; Ex Tempore Judgment
- Outcome
- Zebicon is entitled to judgment and to its costs of the proceedings.
- Legal Topics
- ['security of Payment' 'payment Claim' 'payment Schedule' 'service by Facsimile' 'receipt of Notices' 'fax Transmission Evidence']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Building and Construction Payment Claim Dispute / Preliminary Decision; Ex Tempore Judgment
Legal Issues
- 1 ['What was the precise date on which Zebicon served or first served payment claim 11.' 'What was the precise date on which Remo provided or first provided its payment schedule in response.' "Whether a payment claim sent by fax was received where the recipient's fax machine was faulty and no printout was found." 'Whether Remo provided a payment schedule personally to Mr Zerilli on 4 August 2008.']
Ratio Decidendi
Payment claim 11 was served on Remo on 19 July 2008 because the evidence of Mr Zerilli and the fax transmission report marked OK supported an unrebutted inference that the claim was transmitted to and received into the memory of Remo's fax machine at its ordinary place of business. Receipt did not require printing out or attention by Remo staff, and service by facsimile under s 31(1)(c) was not confined to normal office hours. The Court was not satisfied that Remo gave a payment schedule to Mr Zerilli on 4 August 2008. Zebicon was therefore entitled to judgment.
Court Disposition
Zebicon is entitled to judgment and to its costs of the proceedings.
Orders
- ['The parties are directed to bring in short minutes of order in the course of today, including an agreed calculation of interest and giving credit for any payments that may have been made.' 'The exhibits are to be dealt with in accordance with the rules.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment