Halifax Independent Elementary School Society v. Sackville Trenching Ltd.

Halifax Independent Elementary School Society v. Sackville Trenching Ltd.

Adjudicator found on the balance of probabilities that claimant and its consultant warned the excavator and showed plans; the operator exceeded the instructed depth causing damage to the geothermal pipe; damages for repair were awarded to claimant in the sum claimed less amounts awarded to defendant on its...

Source-derived case information.

Citation
2009 NSSM 10
Parties
Claimant: Halifax Independent Elementary School Society; Defendant: 3071061 Nova Scotia Limited carrying on business as Sackville Trenching Limited
Court
Nova Scotia Small Claims Court
Jurisdiction
Canada
Judgment Date
26 January 2009
Procedural Posture
Small Claims Court / Decision
Outcome
Claimant's claim partly allowed; judgment for Claimant against Defendant in the amount of $15,706.78 after set-offs; no order as to costs.
Legal Topics
Negligence, Breach of Contract, Damages, Counterclaim, Allocation of Costs
Source Language
en
Contract Law Tort (negligence) Property Law Negligence Breach of Contract Damages Counterclaim Allocation of Costs

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Halifax Independent Elementary School Society

Claimant

3071061 Nova Scotia Limited carrying on business as Sackville Trenching Limited

Defendant

Procedural Posture

Small Claims Court / Decision

  1. 1 Whether the defendant negligently or in breach of contract damaged an underground geothermal heating pipe
  2. 2 Whether the claimant provided notice or plans of the underground system to the defendant
  3. 3 Causation and quantification of damages resulting from the damaged geothermal system

Ratio Decidendi

Adjudicator found on the balance of probabilities that claimant and its consultant warned the excavator and showed plans; the operator exceeded the instructed depth causing damage to the geothermal pipe; damages for repair were awarded to claimant in the sum claimed less amounts awarded to defendant on its counterclaim, applying the betterment principle to limit recoverable costs; no order as to costs.

Court Disposition

Claimant's claim partly allowed; judgment for Claimant against Defendant in the amount of $15,706.78 after set-offs; no order as to costs.

Orders

  • Defendant shall pay Claimant $21,859.93 less $3,391.50 less $2,761.65 resulting in a total of $15,706.78
  • No order as to costs