Allterrain Contracting Inc. v. Grafton Developments Inc.
Contract No. 2 was a clear, executed change order that modified Contract No. 1 and released Allterrain from obligation to reinstate flat works in front of The Pearl; Grafton failed to prove its counterclaim on the balance of probabilities; accordingly Allterrain is entitled to judgment for its claimed amounts and may realize on the security Grafton posted to vacate the lien.
- Citation
- 2020 NSSC 66
- Parties
- Plaintiff/defendant by Counterclaim: Allterrain Contracting Inc.; Defendant/plaintiff by Counterclaim: Grafton Developments Inc.
- Court
- Supreme Court of Nova Scotia
- Jurisdiction
- Canada
- Judgment Date
- 20 February 2020
- Procedural Posture
- Construction Contract Dispute (builders' Lien) / Trial Decision / Final Judgment
- Outcome
- Judgment for plaintiff Allterrain Contracting Inc. for $30,569.77; Grafton's counterclaim dismissed; Allterrain may realize on security posted to vacate the lien.
- Legal Topics
- Contract Interpretation, Change Order Effect, Lien Security, Counterclaim for Completion Costs, Permit Fee Reimbursement, Credibility of Witnesses
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Allterrain Contracting Inc.
Plaintiff/defendant by Counterclaim
Grafton Developments Inc.
Defendant/plaintiff by Counterclaim
Procedural Posture
Construction Contract Dispute (builders' Lien) / Trial Decision / Final Judgment
Legal Issues
- 1 Whether Allterrain is entitled to payment for outstanding work under the contracts
- 2 Whether Grafton has a valid counterclaim for completion/deficiency costs
- 3 Whether Allterrain may realize on security paid into court to vacate the lien
Ratio Decidendi
Contract No. 2 was a clear, executed change order that modified Contract No. 1 and released Allterrain from obligation to reinstate flat works in front of The Pearl; Grafton failed to prove its counterclaim on the balance of probabilities; accordingly Allterrain is entitled to judgment for its claimed amounts and may realize on the security Grafton posted to vacate the lien.
Court Disposition
Judgment for plaintiff Allterrain Contracting Inc. for $30,569.77; Grafton's counterclaim dismissed; Allterrain may realize on security posted to vacate the lien.
Orders
- Judgment awarded to Allterrain Contracting Inc. in the sum of $30,569.77.
- Grafton Developments Inc. shall not recover on its counterclaim; counterclaim dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment