Berlinquet v. The Queen

Berlinquet v. The Queen

Majority held appellants had contractually waived claims for extras and could not recover absent the chief engineer's certificate required by statute and contract; contractors abandoned or repudiated the contract, the commissioners lawfully took and completed the work and Crown was entitled to recover excess...

Source-derived case information.

Citation
(1886) 13 SCR 26
Parties
Appellants / Suppliants: François Xavier Berlinguet; Charlotte Mailloux (F. X. Berlinguet & Co.); Respondent / Crown: Her Majesty the Queen (Dominion of Canada)
Court
Supreme Court of Canada
Jurisdiction
Canada
Judgment Date
7 December 1886
Procedural Posture
Petition of Right (contract Dispute) / Appeal to the Supreme Court of Canada (final Hearing/judgment)
Outcome
Appeal dismissed; judgment of Exchequer Court affirmed in substance but varied to account for value of plant/materials to be deducted from Crown counterclaim
Legal Topics
Forfeiture and Penalties, Condition Precedent (engineer's Certificate), Waiver and Estoppel, Extra Works/quantum Meruit, Statutory Payment Procedure (31 Vic. C.13 S.18), Remedies on Governmental Completion of Contract
Source Language
english
Contract Public/administrative Law Procurement/public Works Forfeiture and Penalties Condition Precedent (engineer's Certificate) Waiver and Estoppel Extra Works/quantum Meruit Statutory Payment Procedure (31 Vic. C.13 S.18) +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

François Xavier Berlinguet; Charlotte Mailloux (F. X. Berlinguet & Co.)

Appellants / Suppliants

Her Majesty the Queen (Dominion of Canada)

Respondent / Crown

Procedural Posture

Petition of Right (contract Dispute) / Appeal to the Supreme Court of Canada (final Hearing/judgment)

  1. 1 Whether orders in council and subsequent conduct created a new contract superseding the original lump‑sum contracts
  2. 2 Whether contractors waived claims for extra work and renounced right to recover absent engineer's certificate
  3. 3 Whether the requirement of a certificate by the chief engineer under 31 Vic. c.13 s.18 is a condition precedent to recovery

Ratio Decidendi

Majority held appellants had contractually waived claims for extras and could not recover absent the chief engineer's certificate required by statute and contract; contractors abandoned or repudiated the contract, the commissioners lawfully took and completed the work and Crown was entitled to recover excess completion costs, but value of contractors' plant/materials had to be accounted for (deducted from Crown counterclaim).

Court Disposition

Appeal dismissed; judgment of Exchequer Court affirmed in substance but varied to account for value of plant/materials to be deducted from Crown counterclaim

Orders

  • Appeal dismissed with costs
  • Judgment of Exchequer Court varied to deduct value of plant and materials transferred by contractors (approx. $27,022.35) from the Crown's counterclaim