Blackhawk Construction Limited v. Martin
Security for costs was ordered because Blackhawk, a corporation, failed to rebut the presumption under Rule 45.02(3)(c) by providing detailed evidence of income and capacity to raise security; in all the circumstances it was unfair to allow the claim to proceed without security, and the appropriate amount of security was fixed at $30,000 payable by November 16, 2020.
- Citation
- 2020 NSSC 272
- Parties
- Plaintiff / Defendant by Counterclaim: Blackhawk Construction Limited; Defendants / Plaintiffs by Counterclaim: Gregory Neil Martin; Marjorie Marie Martin
- Court
- Supreme Court of Nova Scotia
- Jurisdiction
- Canada
- Judgment Date
- 2 October 2020
- Procedural Posture
- Civil — Contract and Tort (construction) Dispute / Motion for Security for Costs (pre Trial)
- Outcome
- Motion granted: security for costs ordered
- Legal Topics
- Security for Costs, Impecuniosity / Disclosure, Costs Estimation and Orders, Liens, Personal Property Security Act Searches
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Blackhawk Construction Limited
Plaintiff / Defendant by Counterclaim
Gregory Neil Martin; Marjorie Marie Martin
Defendants / Plaintiffs by Counterclaim
Procedural Posture
Civil — Contract and Tort (construction) Dispute / Motion for Security for Costs (pre Trial)
Legal Issues
- 1 Whether security for costs should be ordered under Civil Procedure Rule 45
- 2 Whether Blackhawk rebutted the rebuttable presumption under Rule 45.02(3)(c) that it will have undue difficulty realizing on a costs award
- 3 Appropriate amount and timing of security for costs
Ratio Decidendi
Security for costs was ordered because Blackhawk, a corporation, failed to rebut the presumption under Rule 45.02(3)(c) by providing detailed evidence of income and capacity to raise security; in all the circumstances it was unfair to allow the claim to proceed without security, and the appropriate amount of security was fixed at $30,000 payable by November 16, 2020.
Court Disposition
Motion granted: security for costs ordered
Orders
- Blackhawk Construction Limited shall post security for costs in the amount of $30,000 CAD
- The security may be paid in installments but the total must be posted with the Court on or before November 16, 2020
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment