Dennis Lively Construction & Backhoe Services Ltd. v. Beaver Bank Children's Learning Centre Ltd.

Dennis Lively Construction & Backhoe Services Ltd. v. Beaver Bank Children's Learning Centre Ltd.

Adjudicator found claimant entitled to most of the claimed balance but liable for specific remedial costs because: (a) claimant's delay in obtaining an electrical controller was not a contractual breach (time not of the essence and delay reasonable), (b) claimant's quote to 'install C3 septic system' reasonably...

Source-derived case information.

Citation
2011 NSSM 53
Parties
Claimant: Dennis Lively Construction & Backhoe Services Ltd.; Defendant: Beaver Bank Children's Learning Centre Ltd.
Court
Nova Scotia Small Claims Court
Jurisdiction
Canada
Judgment Date
31 August 2011
Procedural Posture
Small Claims Court / Decision on Merits (judgment)
Outcome
Judgment for Claimant in the amount of CAD 12,956.09; no interest awarded; costs of CAD 179.35 awarded to Claimant; defendant credit allowed of CAD 5,574.55 against claimed balance.
Legal Topics
Breach of Contract, Set Off/credit, Holdback, Quantum Meruit, Remedies, Costs and Interest
Source Language
english
Contract Law Construction Law Builders' Lien Law Civil Procedure Breach of Contract Set Off/credit Holdback Quantum Meruit +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 1 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Dennis Lively Construction & Backhoe Services Ltd.

Claimant

Beaver Bank Children's Learning Centre Ltd.

Defendant

Procedural Posture

Small Claims Court / Decision on Merits (judgment)

  1. 1 Whether defendant could hire others and offset costs against contract balance
  2. 2 Whether claimant breached by delaying completion
  3. 3 Whether claimant was responsible for electrical hook-up to septic system and liable for related costs

Ratio Decidendi

Adjudicator found claimant entitled to most of the claimed balance but liable for specific remedial costs because: (a) claimant's delay in obtaining an electrical controller was not a contractual breach (time not of the essence and delay reasonable), (b) claimant's quote to 'install C3 septic system' reasonably included the electrical hook-up so defendant allowed credit for $2,241.05, (c) claimant was responsible for bringing septic up to standard and defendant allowed additional septic remediation credit $3,333.50, (d) interceptor trench charge of $1,500 was a reasonable extra, and (e) driveway grading and drainage claims did not justify broader offsets; net result claim reduced by...

Court Disposition

Judgment for Claimant in the amount of CAD 12,956.09; no interest awarded; costs of CAD 179.35 awarded to Claimant; defendant credit allowed of CAD 5,574.55 against claimed balance.

Orders

  • Judgment entered for Dennis Lively Construction & Backhoe Services Ltd. in the amount of $12,956.09.
  • Claim reduced by credits totaling $5,574.55 (electrical work $2,241.05 and other septic work $3,333.50).