Johnston Investments v. Spears
The defendants breached the contract by unilaterally withholding the final contract payment at substantial completion; the written contract including General Conditions governed remedies for deficiencies (warranty available after payment), so the claimant was entitled to the outstanding balance; only proven direct damages (washer and exterior door) were awarded to defendants as setoff totaling $400; claimant awarded balance plus 4% interest and costs.
- Citation
- 2022 NSSM 29
- Parties
- Claimant: Johnston Investments cob as All-Craft; Defendants: Dan & Christine Spears
- Court
- Nova Scotia Small Claims Court
- Jurisdiction
- Canada
- Judgment Date
- 3 August 2022
- Procedural Posture
- Small Claims Court / Decision
- Outcome
- Claimant's claim allowed in part; counterclaim substantially dismissed except for limited damages; claimant awarded outstanding contract balance subject to setoff, interest and costs.
- Legal Topics
- Breach of Contract, Warranty, Allowances and Estimates, Substantial Completion, Payment Schedule, Damages, Setoff, Contract Interpretation
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Johnston Investments cob as All-Craft
Claimant
Dan & Christine Spears
Defendants
Procedural Posture
Small Claims Court / Decision
Legal Issues
- 1 Whether the defendants were contractually entitled to withhold the final 5% payment at substantial completion
- 2 Whether the General Conditions formed part of the contract
- 3 Whether deficiencies alleged by defendants amounted to contractor breach allowing setoff or withholding of payment
Ratio Decidendi
The defendants breached the contract by unilaterally withholding the final contract payment at substantial completion; the written contract including General Conditions governed remedies for deficiencies (warranty available after payment), so the claimant was entitled to the outstanding balance; only proven direct damages (washer and exterior door) were awarded to defendants as setoff totaling $400; claimant awarded balance plus 4% interest and costs.
Court Disposition
Claimant's claim allowed in part; counterclaim substantially dismissed except for limited damages; claimant awarded outstanding contract balance subject to setoff, interest and costs.
Orders
- Claimant entitled to payment of the balance due at substantial completion of $8,190.67 less setoff of $400 (awarded to defendants) resulting in net award of $7,790.67 to claimant
- Award interest on the amount due at 4% from the date payment was due until paid
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment