Schroeder v. LeBlanc
Claimant entitled to reimbursement for provable reasonable cost of supplies used to correct deficiencies ($1,222.73) because she acted reasonably to mitigate after contractor abandoned the job; claimant failed to prove entitlement to reimbursement of the instalment due to acceptance of partial work and lack of valuation; defendant failed to prove counterclaim for lost wages or material mark-up.
- Citation
- 2025 NSSM 25
- Parties
- Claimant: Audrey Schroeder; Defendant: Collin LeBlanc
- Court
- Nova Scotia Small Claims Court
- Jurisdiction
- Canada
- Judgment Date
- 17 May 2025
- Procedural Posture
- Small Claims Court Reimbursement for Construction Expenses / Final Decision (adjudication)
- Outcome
- Claim allowed in part; counterclaim denied
- Legal Topics
- Breach of Contract, Workmanship Defects, Mitigation of Damages, Counterclaim for Lost Wages, Damages Valuation, Building Code Compliance
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Audrey Schroeder
Claimant
Collin LeBlanc
Defendant
Procedural Posture
Small Claims Court Reimbursement for Construction Expenses / Final Decision (adjudication)
Legal Issues
- 1 Whether claimant is entitled to reimbursement of the instalment paid for construction
- 2 Whether claimant is entitled to reimbursement of supplies used to correct workmanship deficiencies
- 3 Whether defendant is entitled to counterclaim for lost wages and loss of material mark-up
Ratio Decidendi
Claimant entitled to reimbursement for provable reasonable cost of supplies used to correct deficiencies ($1,222.73) because she acted reasonably to mitigate after contractor abandoned the job; claimant failed to prove entitlement to reimbursement of the instalment due to acceptance of partial work and lack of valuation; defendant failed to prove counterclaim for lost wages or material mark-up.
Court Disposition
Claim allowed in part; counterclaim denied
Orders
- Award claimant $1,222.73 for costs of supplies
- Counterclaim by defendant denied
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment