Secure Energy Services Inc. - Scheduling Order (s. 104)

Secure Energy Services Inc. - Scheduling Order (s. 104)

The Tribunal exercised its authority under s.104 of the Competition Act and its case management powers to adopt the parties' proposed timetable and issue a scheduling order setting specific dates for respondents' response, applicant's reply, cross-examinations, memoranda and the hearing.

Source-derived case information.

Citation
2021 Comp Trib 5
Parties
Applicant: Commissioner of Competition; Respondent: Secure Energy Services Inc.; Respondent: Tervita Corporation
Court
Competition Tribunal
Jurisdiction
Canada
Judgment Date
7 July 2021
Procedural Posture
Interim Order (mergers) / Scheduling Order Following S.104 Application
Outcome
Scheduling order issued.
Legal Topics
Interim Order, Scheduling, Case Management
Source Language
english
Competition Law Mergers Administrative Law Interim Order Scheduling Case Management

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 2 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Commissioner of Competition

Applicant

Secure Energy Services Inc.

Respondent

Tervita Corporation

Respondent

Procedural Posture

Interim Order (mergers) / Scheduling Order Following S.104 Application

  1. 1 Whether to set an expedited schedule for the s.104 interim application
  2. 2 Appropriate dates for filing responses, cross-examination, written memoranda and hearing

Ratio Decidendi

The Tribunal exercised its authority under s.104 of the Competition Act and its case management powers to adopt the parties' proposed timetable and issue a scheduling order setting specific dates for respondents' response, applicant's reply, cross-examinations, memoranda and the hearing.

Court Disposition

Scheduling order issued.

Orders

  • Respondents’ response and responding application record: July 14, 2021
  • Applicant’s reply (if any): July 19, 2021