Maidstone (Township) v. Loosemore Excavating Inc.

Maidstone (Township) v. Loosemore Excavating Inc.

The Court upheld the trial judge's item-by-item factual findings that portions of the contractor's work breached contractual standards, dismissed the claim against the engineer for lack of expert evidence of negligence, and varied the judgment to add $10,486.00 to the Township's award against the contractor for two...

Source-derived case information.

Citation
C25833
Parties
Appellant: Corporation of the Township of Maidstone; Respondent: Loosemore Excavating Inc.; Respondent: Henry Regts; Respondent: Thames Valley Engineering Inc.; Third Party Respondent: Simcoe & Erie General Insurance Company
Court
Court of Appeal for Ontario
Jurisdiction
Canada
Judgment Date
2 December 1998
Procedural Posture
Civil (construction/contract) / Appeal; Court of Appeal Judgment
Outcome
Appeal and cross-appeals dismissed except as to variation of damages in favour of the Township; judgment against Loosemore Excavating Inc. increased.
Legal Topics
Defective Work, Engineer Negligence, Assessment of Damages, Costs and Solicitor Client Costs, Standard of Care, Expert Evidence
Source Language
en
Construction Law Contract Law Professional Negligence Civil Procedure Costs Defective Work Engineer Negligence Assessment of Damages +3 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 2 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Corporation of the Township of Maidstone

Appellant

Loosemore Excavating Inc.

Respondent

Henry Regts

Respondent

Thames Valley Engineering Inc.

Respondent

Simcoe & Erie General Insurance Company

Third Party Respondent

Procedural Posture

Civil (construction/contract) / Appeal; Court of Appeal Judgment

  1. 1 Whether the contractor's work met the contractual standard
  2. 2 Whether the project engineer was negligent in approving the work
  3. 3 Whether the Township took appropriate steps to correct deficiencies

Ratio Decidendi

The Court upheld the trial judge's item-by-item factual findings that portions of the contractor's work breached contractual standards, dismissed the claim against the engineer for lack of expert evidence of negligence, and varied the judgment to add $10,486.00 to the Township's award against the contractor for two omitted items.

Court Disposition

Appeal and cross-appeals dismissed except as to variation of damages in favour of the Township; judgment against Loosemore Excavating Inc. increased.

Orders

  • Vary trial judgment: add $10,486.00 to the Township's award against Loosemore Excavating Inc.
  • Affirm all other amounts awarded and the contractor's counterclaim judgment of $4,484.44