Maidstone (Township) v. Loosemore Excavating Inc.
The Court upheld the trial judge's item-by-item factual findings that portions of the contractor's work breached contractual standards, dismissed the claim against the engineer for lack of expert evidence of negligence, and varied the judgment to add $10,486.00 to the Township's award against the contractor for two...
Source-derived case information.
- Citation
- C25833
- Parties
- Appellant: Corporation of the Township of Maidstone; Respondent: Loosemore Excavating Inc.; Respondent: Henry Regts; Respondent: Thames Valley Engineering Inc.; Third Party Respondent: Simcoe & Erie General Insurance Company
- Court
- Court of Appeal for Ontario
- Jurisdiction
- Canada
- Judgment Date
- 2 December 1998
- Procedural Posture
- Civil (construction/contract) / Appeal; Court of Appeal Judgment
- Outcome
- Appeal and cross-appeals dismissed except as to variation of damages in favour of the Township; judgment against Loosemore Excavating Inc. increased.
- Legal Topics
- Defective Work, Engineer Negligence, Assessment of Damages, Costs and Solicitor Client Costs, Standard of Care, Expert Evidence
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Corporation of the Township of Maidstone
Appellant
Loosemore Excavating Inc.
Respondent
Henry Regts
Respondent
Thames Valley Engineering Inc.
Respondent
Simcoe & Erie General Insurance Company
Third Party Respondent
Procedural Posture
Civil (construction/contract) / Appeal; Court of Appeal Judgment
Legal Issues
- 1 Whether the contractor's work met the contractual standard
- 2 Whether the project engineer was negligent in approving the work
- 3 Whether the Township took appropriate steps to correct deficiencies
Ratio Decidendi
The Court upheld the trial judge's item-by-item factual findings that portions of the contractor's work breached contractual standards, dismissed the claim against the engineer for lack of expert evidence of negligence, and varied the judgment to add $10,486.00 to the Township's award against the contractor for two omitted items.
Court Disposition
Appeal and cross-appeals dismissed except as to variation of damages in favour of the Township; judgment against Loosemore Excavating Inc. increased.
Orders
- Vary trial judgment: add $10,486.00 to the Township's award against Loosemore Excavating Inc.
- Affirm all other amounts awarded and the contractor's counterclaim judgment of $4,484.44
Full Case Text
Judgment text and source record
1 paragraphs
Maidstone (Township) v. Loosemore Excavating Inc. Collection Decisions of the Court of Appeal Date 1998-12-02 Docket numbers C25833 Judges Krever, Horace; Labrosse, Jean-Marc; Doherty, David H. Subject Civil Decision Content DATE: 1998122 DOCKET: C25833 COURT OF APPEAL FOR ONTARIO RE: CORPORATION OF THE TOWNSHIP OF MAIDSTONE (Plaintiff (Appellant)) v. LOOSEMORE EXCAVATING INC., HENRY REGTS AND THAMES VALLEY ENGINEERING INC. (Defendants (Respondents)) and SIMCOE & ERIE GENERAL INSURANCE COMPANY (Third Party (Respondent)) BEFORE: KREVER, LABROSSE and DOHERTY JJ.A. COUNSEL: Richard A. Dinham and Brian McAllister for the appellant Raymond G. Colautti and Craig M. Houle for the respondent Regts and Thames Valley Engineering Inc. James A. LeBer for the respondent Loosemore Excavating Inc. HEARD: November 25, 1998 E N D O R S E M E N T [1] This is an appeal and cross-appeal from the judgment granting the Township of Maidstone judgment against the contractor Loosemore Excavating Inc. in the amount of $61,793.54 plus interest and granting the contractor judgment on its counterclaim against the Township in the amount of $4,484.44. The action arises from the design and construction of a drain and pumping station and related work. [2] The Township's claim against the contractor and the contractor's counterclaim both required an assessment of competing opinion evidence as to the quality of the contractor's work and the steps needed to correct deficiencies in that work. That evidence was directed to numerous aspects of the work done and was both detailed and technical. The trial judge made a careful item-by-item assessment of the claims and the competing evidence. Apart from two relatively minor matters, we see no basis upon which we can interfere with his findings. Those two matters are: * Item 20 - concrete under the CNR bridge ($8,560.00): The trial judge found that the contractor's work was below the standard required under the contract. He disallowed this claim on the basis that the Township had failed to show that it had used the "most reasonable" means available to correct the deficiency in the work. In our view, the Township was not required to meet that onus, but was only required to show that the steps taken were an appropriate response to the problem created by the deficiency. The Township met that standard. * Drain excavation on County Road 46 ($1,926.00): This claim was not referred to by the trial judge in his reasons. His failure to allow this claim was clearly an oversight in that he did allow an identical claim relating to drain excavation on another county road. [3] We would vary the award made in favour of the Township against the contractor by adding $10,486.00 ($8,560.00 plus $1,926.00). We would not otherwise disturb the amounts awarded on the claim or the counterclaim. [4] In its cross-appeal on the counterclaim, the contractor also contended that as the engineer approved its work, there could be no finding that its work failed to meet the standard set out in the contract absent a finding that the engineer was negligent. Not only was there no such finding, the trial judge found that the engineer was not negligent. [5] It does not follow that a failure to prove that the engineer fell below the applicable standard in approving work done by the contractor necessitates a finding that the work done was in accordance with the standards set in the contract. These are two distinct issues. There was ample evidence that parts of the contractor's work fell below the standard required by the contract. Indeed, the real question at trial was not whether any of the work fell below that standard but rather, how much of the work failed to meet that standard. [6] There was also a claim by the Township and a cross-claim by the contractor against the project engineer. Both were dismissed and the engineer was awarded costs as against the Township, which costs were added to the costs awarded to the Township against the contractor. The Township appeals from the trial judge's finding that it had not shown that the engineer was negligent. [7] The allegation that the engineer was negligent was fully canvassed by the trial judge who properly concluded that there was no expert evidence as to the applicable standard of care and no evidence that the standard was not met by the engineer. In the absence of such evidence, we can find no error in the trial judge's conclusion that the Township failed to prove that the engineer was negligent. [8] Finally, we see no error in the trial judge's disposition of the costs. In particular, we are not satisfied that he erred in the exercise of his discretion in refusing to grant the engineer solicitor and client costs. [9] Save for the relatively minor variation in the amount awarded to the Township on its claim against the contractor, we would dismiss the appeal and the cross appeals. The successful parties on each of the appeals are entitled to their costs of that appeal.