Dexter Construction Company Ltd. v. Nova Scotia (Attorney General)

Dexter Construction Company Ltd. v. Nova Scotia (Attorney General)

Clause 3.3 applied because the contracts were carried over to the next calendar year and the conditions (notably lateness of tender calls and completion dates in 2006 noted in special provisions) for the Department to consider a price adjustment were met; the Department therefore had a duty to consider and should...

Source-derived case information.

Citation
2011 NSSC 441
Parties
Plaintiff: Dexter Construction Company Limited; Defendant: The Attorney General of Nova Scotia, representing Her Majesty the Queen in right of the Province of Nova Scotia
Court
Supreme Court of Nova Scotia
Jurisdiction
Canada
Judgment Date
30 November 2011
Procedural Posture
Contract Dispute / Trial Judgment
Outcome
Judgment for the plaintiff
Legal Topics
Contract Interpretation, Price Escalation Clause, Damages, Pre Judgment Interest
Source Language
en
Contract Law Construction Law Procurement Contract Interpretation Price Escalation Clause Damages Pre Judgment Interest

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Dexter Construction Company Limited

Plaintiff

The Attorney General of Nova Scotia, representing Her Majesty the Queen in right of the Province of Nova Scotia

Defendant

Procedural Posture

Contract Dispute / Trial Judgment

  1. 1 Whether the contracts contain an escalator clause (clause 3.3 of Standard Specification Division 4 Section 2) entitling Dexter to compensation for increased PGAB prices
  2. 2 Whether the Department had a duty to consider a price adjustment under clause 3.3 once its preconditions were met
  3. 3 Whether the contracts were 'carried over to the next calendar year' for the purposes of clause 3.3

Ratio Decidendi

Clause 3.3 applied because the contracts were carried over to the next calendar year and the conditions (notably lateness of tender calls and completion dates in 2006 noted in special provisions) for the Department to consider a price adjustment were met; the Department therefore had a duty to consider and should have exercised its discretion to allow Dexter to charge the actual PGAB price, entitling Dexter to damages of $522,000 plus agreed prejudgment interest.

Court Disposition

Judgment for the plaintiff

Orders

  • Defendant shall pay Dexter Construction Company Limited the sum of $522,000.00.
  • Defendant shall pay prejudgment interest to Dexter Construction Company Limited at the rate of 5% per annum.