Derago v. Doctor
The handwritten contemporaneous sketch showing a stepped fence and the defendant's credible evidence established the agreed specification; the claimant's work did not conform to that contractual specification, had no value to the defendant, and therefore the claimant was not entitled to payment.
Source-derived case information.
- Citation
- 2017 NSSM 58
- Parties
- Claimant: Mladen Derago; Defendant: Faun Doctor
- Court
- Nova Scotia Small Claims Court
- Jurisdiction
- Canada
- Judgment Date
- 27 October 2017
- Procedural Posture
- Small Claims Court / Decision
- Outcome
- Claim dismissed
- Legal Topics
- Breach of Contract, Oral Contract, Scope of Work, Damages, Credibility
- Source Language
- english
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Mladen Derago
Claimant
Faun Doctor
Defendant
Procedural Posture
Small Claims Court / Decision
Legal Issues
- 1 Whether the claimant performed work in accordance with the contract
- 2 Whether the claimant is entitled to payment for partial performance
- 3 Whether the defendant suffered loss and mitigation by hiring another contractor
Ratio Decidendi
The handwritten contemporaneous sketch showing a stepped fence and the defendant's credible evidence established the agreed specification; the claimant's work did not conform to that contractual specification, had no value to the defendant, and therefore the claimant was not entitled to payment.
Court Disposition
Claim dismissed
Orders
- The claim is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment