Frank E. Illsley Woodworking Ltd. v. D & M Lightfoot Farms Ltd.

Frank E. Illsley Woodworking Ltd. v. D & M Lightfoot Farms Ltd.

The Sale of Goods Act s.17(a) was not triggered because the buyer did not make known the particular purpose (suspended equipment loads) in sufficient detail; both parties (Illsley and Roscoe) breached duties by failing to ascertain or provide the pertinent dead load information and were equally negligent; therefore...

Source-derived case information.

Citation
2004 NSSC 40
Parties
Plaintiff: Frank E. Illsley Woodworking Limited; Defendant: D & M Lightfoot Farms Limited; Defendant: Roscoe Construction Limited
Court
Supreme Court of Nova Scotia
Jurisdiction
Canada
Judgment Date
26 January 2004
Procedural Posture
Civil Contract Action (sale of Goods/construction) / Trial Judgment
Outcome
Judgment for plaintiff Frank E. Illsley Woodworking Limited against Roscoe Construction Limited in the amount of $76,975.54 (including pre-judgment interest); parties found equally at fault; costs to be determined or submitted.
Legal Topics
Fitness for Particular Purpose, Negligent Performance of Contract, Contributory Negligence, Damages Calculation, Pre Judgment Interest, Restocking Credit, Insurance Proceeds
Source Language
en
Contract Law Tort Negligence Sale of Goods Construction Law Insurance Law Fitness for Particular Purpose Negligent Performance of Contract Contributory Negligence +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 11
Sign in to unlock

Parties

Frank E. Illsley Woodworking Limited

Plaintiff

D & M Lightfoot Farms Limited

Defendant

Roscoe Construction Limited

Defendant

Procedural Posture

Civil Contract Action (sale of Goods/construction) / Trial Judgment

  1. 1 Whether Sale of Goods Act s.17(a) (fitness for particular purpose/reliance) was engaged
  2. 2 Which party was responsible for failing to ascertain/provide equipment/dead loads for truss design
  3. 3 Whether negligent performance of contract applies and apportionment of fault

Ratio Decidendi

The Sale of Goods Act s.17(a) was not triggered because the buyer did not make known the particular purpose (suspended equipment loads) in sufficient detail; both parties (Illsley and Roscoe) breached duties by failing to ascertain or provide the pertinent dead load information and were equally negligent; therefore damages for the additional cost of redesigned trusses are shared equally, restocking credit is apportioned, and insurer surplus is not payable to plaintiff.

Court Disposition

Judgment for plaintiff Frank E. Illsley Woodworking Limited against Roscoe Construction Limited in the amount of $76,975.54 (including pre-judgment interest); parties found equally at fault; costs to be determined or submitted.

Orders

  • Judgment for plaintiff in the principal sum of $70,619.77 plus pre-judgment interest of $6,355.77 (total $76,975.54).
  • Roscoe Construction Limited liable to pay Illsley one half of additional redesign costs; restocking credit to Roscoe of $10,752.50 applied.