Hickey's Building Supplies Limited v. Sheppard

Hickey's Building Supplies Limited v. Sheppard

Where the contractor had actual knowledge of the owner's special needs and the contract aimed to secure peace of mind (wheelchair accessibility), the contractor was bound to deliver level flooring notwithstanding minimum Building Code tolerances; damages for remediation and for non-delivered contractual benefits...

Source-derived case information.

Citation
2014 NLCA 43
Parties
Appellant: Hickey’s Building Supplies Limited; Respondent: Harvey Sheppard; Respondent: Patsy Sheppard
Court
Newfoundland and Labrador Court of Appeal
Jurisdiction
Canada
Judgment Date
24 November 2014
Procedural Posture
Appeal From Trial Decision (contract / Construction Dispute) / Court of Appeal Judgment
Outcome
Appeal allowed in part and dismissed in part. Trial judge's findings that contractor must remediate flooring and compensate for nine-foot ceiling shortfall and award $15,000 general damages were upheld by the majority; mechanics' lien reinstated in adjusted amount; costs awarded to respondents under contract and...
Legal Topics
Breach of Contract, Contract Interpretation, General (mental Distress) Damages, Mechanics' Lien, Waiver, Standard of Review
Source Language
en
Contract Law Construction Law Mechanics' Lien Law Remedies and Damages Costs Law Breach of Contract Contract Interpretation General (mental Distress) Damages +3 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Hickey’s Building Supplies Limited

Appellant

Harvey Sheppard

Respondent

Patsy Sheppard

Respondent

Procedural Posture

Appeal From Trial Decision (contract / Construction Dispute) / Court of Appeal Judgment

  1. 1 Whether the trial judge erred in awarding damages for (a) failure to provide a level floor and (b) failure to provide nine-foot ceilings
  2. 2 Whether the trial judge erred in awarding general (non-pecuniary) damages for mental distress
  3. 3 Whether the mechanics' lien was properly vacated

Ratio Decidendi

Where the contractor had actual knowledge of the owner's special needs and the contract aimed to secure peace of mind (wheelchair accessibility), the contractor was bound to deliver level flooring notwithstanding minimum Building Code tolerances; damages for remediation and for non-delivered contractual benefits (e.g. ceiling height) are recoverable; mental distress damages are recoverable because the contract's object included psychological benefit within the parties' contemplation; a mechanics' lien should not be vacated where sums remain owing and must be reinstated to the proper net amount after accounting for recoverable setoffs and awards.

Court Disposition

Appeal allowed in part and dismissed in part. Trial judge's findings that contractor must remediate flooring and compensate for nine-foot ceiling shortfall and award $15,000 general damages were upheld by the majority; mechanics' lien reinstated in adjusted amount; costs awarded to respondents under contract and...

Orders

  • Mechanics' lien reinstated in the amount of $35,940.46
  • Contractor to pay remediation for flooring $42,237.87