Aiken Bros. Hardware Limited v. Sargeant

Aiken Bros. Hardware Limited v. Sargeant

The Court held that s.23(2) limits an owner's personal liability to lien claimants to the statutory holdback required by s.22(1); an overpayment by the owner in excess of the 90% allowance under s.24(1) does not create an additional cause of action by subcontractors for the overpaid amount. The appeal was allowed...

Source-derived case information.

Citation
C43365
Parties
Respondent: Aiken Bros. Hardware Limited; Respondent: Greg Brady Construction Ltd.; Appellant: Jean Elizabeth Sargeant; Appellant: John Sloan Sargeant; Appellant: Timothy Fiegehen (TAF Contracting); Appellant: Royal Bank of Canada
Court
Court of Appeal for Ontario
Jurisdiction
Canada
Judgment Date
24 February 2006
Procedural Posture
Civil Construction Lien Appeal / Appeal to Court of Appeal for Ontario From Divisional Court (judgment)
Outcome
Appeal allowed; judgment of the Divisional Court set aside; trial judge's decision reinstated as adjusted by Hambly J.
Legal Topics
Construction Lien Act, Statutory Holdback, Overpayment, Owner Liability to Subcontractors, Interpretation of S.24(1) and S.23(2)
Source Language
en
Construction Law Property Law Civil Procedure Security for Payment Construction Lien Act Statutory Holdback Overpayment Owner Liability to Subcontractors +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Aiken Bros. Hardware Limited

Respondent

Greg Brady Construction Ltd.

Respondent

Jean Elizabeth Sargeant

Appellant

John Sloan Sargeant

Appellant

Timothy Fiegehen (TAF Contracting)

Appellant

Royal Bank of Canada

Appellant

Procedural Posture

Civil Construction Lien Appeal / Appeal to Court of Appeal for Ontario From Divisional Court (judgment)

  1. 1 Whether an owner who overpays a contractor in excess of 90% under s.24(1) of the Construction Lien Act is liable to subcontractors for the amount of the overpayment in addition to the statutory 10% holdback
  2. 2 Whether s.23(2) limits an owner's personal liability to lien claimants to the statutory holdback when the contractor is the defaulting payer

Ratio Decidendi

The Court held that s.23(2) limits an owner's personal liability to lien claimants to the statutory holdback required by s.22(1); an overpayment by the owner in excess of the 90% allowance under s.24(1) does not create an additional cause of action by subcontractors for the overpaid amount. The appeal was allowed and the trial judge's decision reinstated as adjusted by Hambly J.

Court Disposition

Appeal allowed; judgment of the Divisional Court set aside; trial judge's decision reinstated as adjusted by Hambly J.

Orders

  • Reinstate trial judge's judgment as adjusted by Hambly J.
  • Parties to deliver written submissions on costs of the appeal in this Court and in the Divisional Court within 15 days of release of reasons.