Modern Construction Ltd. v. Maritime Rock Products Ltd.

Modern Construction Ltd. v. Maritime Rock Products Ltd.

The contract required completion of all work shown in the specifications; uncontradicted evidence established completion only about September 27, 1961, thus the last work was within 45 days of registration of the lien and the lien filing was timely; there was sufficient evidence of the defendant's interest in the...

Source-derived case information.

Citation
[1963] SCR 347
Parties
Plaintiff/appellant: Modern Construction Limited; Defendant/respondent: Maritime Rock Products Limited
Court
Supreme Court of Canada
Jurisdiction
Canada
Judgment Date
24 June 1963
Procedural Posture
Mechanics' Lien Action / Appeal to the Supreme Court of Canada From Supreme Court of Nova Scotia
Outcome
Appeal allowed; judgments below set aside; action referred back to trial judge for further proceedings
Legal Topics
Mechanics' Lien, Completion of Contract, Interest in Land, Nonsuit, Remittal to Trial
Source Language
english
Property Construction Law Civil Procedure Mechanics' Lien Completion of Contract Interest in Land Nonsuit Remittal to Trial

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Legal principles 3 Authorities cited 10 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Modern Construction Limited

Plaintiff/appellant

Maritime Rock Products Limited

Defendant/respondent

Procedural Posture

Mechanics' Lien Action / Appeal to the Supreme Court of Canada From Supreme Court of Nova Scotia

  1. 1 Whether the last work under the contract was performed within 45 days of filing the lien as required by s.23 of the Mechanics' Lien Act
  2. 2 Whether the defendant had an estate or interest in the lands described sufficient to support a mechanics' lien
  3. 3 Whether nonsuit was correctly granted and if not whether the case should be finally determined or remitted for trial

Ratio Decidendi

The contract required completion of all work shown in the specifications; uncontradicted evidence established completion only about September 27, 1961, thus the last work was within 45 days of registration of the lien and the lien filing was timely; there was sufficient evidence of the defendant's interest in the lands to support the lien; the nonsuit was wrongly granted and the matter is to be remitted to the trial judge for further proceedings.

Court Disposition

Appeal allowed; judgments below set aside; action referred back to trial judge for further proceedings

Orders

  • Set aside the judgment of the Supreme Court of Nova Scotia in banco and the trial judgment dismissing the lien claim
  • Refer the action back to the trial judge for trial to proceed in the usual course