Canadian Comstock v. Toronto Transit Commission
Owner was entitled to the protection of s.11(6) because it had made no payment after notice and confined its claim for non-completion to the additional certified-but-unpaid sums; consequently the subcontractors could not compel those additional funds to be applied to their liens beyond the statutory holdback, and the Court dismissed the appeals affirming the Court of Appeal's allocation of priority.
- Citation
- [1970] SCR 205
- Parties
- Appellant Subcontractor: Canadian Comstock Company Limited; Respondent Owner: Toronto Transit Commission; Respondent Owner: Municipality of Metropolitan Toronto; Respondent Trustee of Bankrupt Contractor: Trustee of the Estate of Anglin-Norcross Ontario Limited, a Bankrupt
- Court
- Supreme Court of Canada
- Jurisdiction
- Canada
- Judgment Date
- 21 October 1969
- Procedural Posture
- Mechanics' Lien Appeal (construction) / Appeal to Supreme Court of Canada From Court of Appeal for Ontario; Final Judgment
- Outcome
- Appeals dismissed with costs; Court of Appeal decision affirmed
- Legal Topics
- Mechanics' Liens, Statutory Holdback, Set Off, Priority of Claims, Contract Abandonment
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Canadian Comstock Company Limited
Appellant Subcontractor
Toronto Transit Commission
Respondent Owner
Municipality of Metropolitan Toronto
Respondent Owner
Trustee of the Estate of Anglin-Norcross Ontario Limited, a Bankrupt
Respondent Trustee of Bankrupt Contractor
Procedural Posture
Mechanics' Lien Appeal (construction) / Appeal to Supreme Court of Canada From Court of Appeal for Ontario; Final Judgment
Legal Issues
- 1 Whether subcontractors holding mechanics' liens are entitled to claim against additional certified-but-unpaid sums held by the owner beyond the statutory holdback
- 2 Whether owner may assert a right of set-off for completion costs and damages against those additional sums
- 3 Effect of s.11(6) (payments made in good faith before notice) on priority
Ratio Decidendi
Owner was entitled to the protection of s.11(6) because it had made no payment after notice and confined its claim for non-completion to the additional certified-but-unpaid sums; consequently the subcontractors could not compel those additional funds to be applied to their liens beyond the statutory holdback, and the Court dismissed the appeals affirming the Court of Appeal's allocation of priority.
Court Disposition
Appeals dismissed with costs; Court of Appeal decision affirmed
Orders
- Appeals dismissed with costs.
- Owner entitled to set-off against additional certified-but-unpaid sums in its hands beyond the statutory holdback; subcontractors limited to statutory holdback and amounts recoverable under the Act.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment