Forward v. Millside Contractors Ltd.

Forward v. Millside Contractors Ltd.

Defendant breached the implied term to perform work in a good and workmanlike manner by failing to follow the manufacturer's installation instructions (nailing and sealing requirements for high-wind areas), which contributed to some shingles blowing off; however, the claimant's full roof replacement was excessive...

Source-derived case information.

Citation
2014 NSSM 69
Parties
Claimant: Sheryl-Lynn Forward; Claimant: Scott William Young; Defendant: Millside Contractors Limited
Court
Nova Scotia Small Claims Court
Jurisdiction
Canada
Judgment Date
14 November 2014
Procedural Posture
Small Claims Breach of Contract / Adjudicator Decision
Outcome
Claimant partially successful; judgment for claimants against Millside Contractors Limited in the amount of $1,100
Legal Topics
Breach of Contract, Implied Terms Workmanlike Performance, Damages, Manufacturer Installation Guidelines, Warranty and High Wind Specifications
Source Language
english
Contract Law Construction Law Consumer Protection Breach of Contract Implied Terms Workmanlike Performance Damages Manufacturer Installation Guidelines Warranty and High Wind Specifications

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Sheryl-Lynn Forward

Claimant

Scott William Young

Claimant

Millside Contractors Limited

Defendant

Procedural Posture

Small Claims Breach of Contract / Adjudicator Decision

  1. 1 Whether the defendant installed shingles in a good and workmanlike manner consistent with the contract and industry/manufacturer standards
  2. 2 Whether failure to follow manufacturer's installation instructions caused shingles to blow off
  3. 3 Appropriate measure of damages given partial breach and mitigation options

Ratio Decidendi

Defendant breached the implied term to perform work in a good and workmanlike manner by failing to follow the manufacturer's installation instructions (nailing and sealing requirements for high-wind areas), which contributed to some shingles blowing off; however, the claimant's full roof replacement was excessive and damages are limited to a proportionate remedy of $1,000 plus modest costs.

Court Disposition

Claimant partially successful; judgment for claimants against Millside Contractors Limited in the amount of $1,100

Orders

  • Defendant to pay damages to claimants in the amount of $1000 CAD
  • Defendant to pay costs to claimants in the amount of $100 CAD