Corpex (1977) Inc. v. The Queen in right of Canada
Clause 12 creates a contractual compensation mechanism for unforeseen soil conditions and requires the contractor to give timely written notice to preserve claims; failure to give notice bars the soil-mistake claim and precludes annulment. Costs caused by delays from work ordered under clause 38 are recoverable under clauses 38 and 46 (actual cost plus 10%), so the contractor is entitled to the quantified delay-related sums; appeal allowed in part awarding those amounts.
- Citation
- [1982] 2 SCR 643
- Parties
- Appellant/contractor: Corpex (1977) Inc.; Respondent/owner: Her Majesty The Queen in right of Canada
- Court
- Supreme Court of Canada
- Jurisdiction
- Canada
- Judgment Date
- 23 November 1982
- Procedural Posture
- Contract Appeal / On Appeal to the Supreme Court of Canada From the Federal Court of Appeal; Final Judgment
- Outcome
- Appeal allowed in part; Federal Court of Appeal judgment reversed in part and Trial Division judgment varied
- Legal Topics
- Mistake, Notice Requirement, Contract Interpretation, Compensation for Extra Work, Delay Claims, Quantum Meruit, Annulment
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Corpex (1977) Inc.
Appellant/contractor
Her Majesty The Queen in right of Canada
Respondent/owner
Procedural Posture
Contract Appeal / On Appeal to the Supreme Court of Canada From the Federal Court of Appeal; Final Judgment
Legal Issues
- 1 Whether the contract could be annulled for mistake as to soil conditions
- 2 Whether contractor may recover additional pumping costs where contractor failed to give notice required by clause 12
- 3 Whether costs arising from delays caused by work ordered in addition to plans/specifications are recoverable under clauses 38 and 46
Ratio Decidendi
Clause 12 creates a contractual compensation mechanism for unforeseen soil conditions and requires the contractor to give timely written notice to preserve claims; failure to give notice bars the soil-mistake claim and precludes annulment. Costs caused by delays from work ordered under clause 38 are recoverable under clauses 38 and 46 (actual cost plus 10%), so the contractor is entitled to the quantified delay-related sums; appeal allowed in part awarding those amounts.
Court Disposition
Appeal allowed in part; Federal Court of Appeal judgment reversed in part and Trial Division judgment varied
Orders
- Action allowed for $138,486.65 with interest at the legal rate from December 5, 1974
- Contract not annulled
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment