Desrosiers et al. v. Gauthier
The Court held that where the penal clause is for delay the creditor may claim both the extra cost to complete the work (or compensatory damages) and the liquidated damages for delay under art.1133 C.C.; here the reasonable delay was assessed at 45 days ($4,500) but the Superior Court had awarded $5,459.05 without deducting the $4,500 second instalment the contractor would have earned, so the excess $4,500 is set off against the penalty leaving a net entitlement of $959.05; appeal dismissed.
- Citation
- [1978] 1 SCR 308
- Parties
- Appellant (plaintiff): Marcel Desrosiers; Appellant (plaintiff): Adélard Dufour; Respondent (defendant): Jean‑Marie Gauthier; Respondent (defendant in Continuance): Dame Gisèle Thibeault
- Court
- Supreme Court of Canada
- Jurisdiction
- Canada
- Judgment Date
- 29 April 1977
- Procedural Posture
- Contract / Appeal to Supreme Court of Canada From Court of Appeal for Quebec
- Outcome
- Appeal dismissed
- Legal Topics
- Penal Clause, Delay in Performance, Partial Performance, Set‑off, Liquidated Damages, Calculation of Moratory Damages
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Marcel Desrosiers
Appellant (plaintiff)
Adélard Dufour
Appellant (plaintiff)
Jean‑Marie Gauthier
Respondent (defendant)
Dame Gisèle Thibeault
Respondent (defendant in Continuance)
Procedural Posture
Contract / Appeal to Supreme Court of Canada From Court of Appeal for Quebec
Legal Issues
- 1 Whether an owner may recover both the extra cost to complete partially performed work and liquidated damages under a penal clause for delay
- 2 Whether a penal clause for delay survives unilateral abandonment of contract and can be joined with compensatory damages
- 3 How to calculate the period for which liquidated damages apply where work is incomplete
Ratio Decidendi
The Court held that where the penal clause is for delay the creditor may claim both the extra cost to complete the work (or compensatory damages) and the liquidated damages for delay under art.1133 C.C.; here the reasonable delay was assessed at 45 days ($4,500) but the Superior Court had awarded $5,459.05 without deducting the $4,500 second instalment the contractor would have earned, so the excess $4,500 is set off against the penalty leaving a net entitlement of $959.05; appeal dismissed.
Court Disposition
Appeal dismissed
Orders
- Appeal dismissed
- Set off $4,500 penal damages against the $4,500 excess awarded by the Superior Court resulting in owner’s net additional entitlement of $959.05
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment