Next Level Contracting v. McQuade
Claimant proved performance of the core contract (pouring concrete around pool) but failed to prove entitlement to extras because the contract required written authorization and credible evidence was lacking; defendant admitted owing $1,750 which establishes liability for that amount; defendant's allegations of poor workmanship and damages were not evidenced and he expressly declined monetary relief, so counterclaim fails; award limited to admitted unpaid balance plus costs.
- Citation
- 2010 NSSM 18
- Parties
- Claimant: Next Level Contracting; Defendant: Randall McQuade
- Court
- Nova Scotia Small Claims Court
- Jurisdiction
- Canada
- Judgment Date
- 18 March 2010
- Procedural Posture
- Small Claims Contract / Decision
- Outcome
- Claim partly allowed. Judgment entered for claimant for outstanding contract balance and costs.
- Legal Topics
- Nonpayment, Extras/variation, Counterclaim for Damages, Quick Judgment / Setting Aside
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Next Level Contracting
Claimant
Randall McQuade
Defendant
Procedural Posture
Small Claims Contract / Decision
Legal Issues
- 1 Whether claimant proved entitlement to full claimed amount for contracted work and claimed extras
- 2 Whether extras were enforceable absent written variation as required by the parties' agreement
- 3 Whether defendant proved counterclaim/damages for alleged poor workmanship
Ratio Decidendi
Claimant proved performance of the core contract (pouring concrete around pool) but failed to prove entitlement to extras because the contract required written authorization and credible evidence was lacking; defendant admitted owing $1,750 which establishes liability for that amount; defendant's allegations of poor workmanship and damages were not evidenced and he expressly declined monetary relief, so counterclaim fails; award limited to admitted unpaid balance plus costs.
Court Disposition
Claim partly allowed. Judgment entered for claimant for outstanding contract balance and costs.
Orders
- Defendant to pay claimant $1750.00
- Defendant to pay court costs $89.68
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment