Reid Developments Ltd. v. Hopkins

Reid Developments Ltd. v. Hopkins

The LOA was a cost-plus contract; the May 2019 preliminary budget was an estimate only and was rendered obsolete by later drawings, specifications and owner-authorized changes; the plaintiff gave adequate notice and cost information during performance; the Hopkins authorized and received the benefit of the work but...

Source-derived case information.

Citation
2025 BCSC 502
Parties
Plaintiff: Reid Developments Ltd.; Defendants: Eric Quay Hopkins and Kandace Dawn Hopkins
Court
Supreme Court of British Columbia
Jurisdiction
Canada
Judgment Date
20 March 2025
Procedural Posture
Contract Dispute — Construction (cost Plus) With Builder's Lien Claim / Trial Judgment (reasons for Judgment)
Outcome
Judgment for plaintiff Reid Developments Ltd.; counterclaim of Hopkins dismissed.
Legal Topics
Cost Plus Contract, Preliminary Budget Estimates, Scope Changes and Extras, Oral Guarantees, Pre Judgment Interest, Builder's Lien, Contract Management and Invoicing
Source Language
english
Construction Law Contract Law Property Law (builder's Lien) Guarantees and Suretyship Civil Procedure Cost Plus Contract Preliminary Budget Estimates Scope Changes and Extras +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Reid Developments Ltd.

Plaintiff

Eric Quay Hopkins and Kandace Dawn Hopkins

Defendants

Procedural Posture

Contract Dispute — Construction (cost Plus) With Builder's Lien Claim / Trial Judgment (reasons for Judgment)

  1. 1 Was the Letter of Agreement (LOA) a cost-plus contract?
  2. 2 Did Reid Developments guarantee completion within the preliminary budget or within 15% of that budget?
  3. 3 Did the preliminary budget restrict the parties' obligations under the LOA?

Ratio Decidendi

The LOA was a cost-plus contract; the May 2019 preliminary budget was an estimate only and was rendered obsolete by later drawings, specifications and owner-authorized changes; the plaintiff gave adequate notice and cost information during performance; the Hopkins authorized and received the benefit of the work but refused to pay the final invoices, so they are liable for $650,209.55 plus recoverable financing costs and pre-judgment interest, and the plaintiff is entitled to a first-priority builder's lien; the alleged oral 15% cap guarantee is not proven and fails statutory formalities.

Court Disposition

Judgment for plaintiff Reid Developments Ltd.; counterclaim of Hopkins dismissed.

Orders

  • Award to plaintiff of damages for breach of contract in the principal amount of 650209.55 CAD.
  • Pre-judgment interest ordered on all unpaid invoice balances from their respective invoice dates (May 18, 2021; June 24, 2021; July 20, 2021) with rate to be determined by court order process (contractual RBC-prime clause not applied).