Thomas v. S. Bennett Construction #863931028
On the balance of probabilities the adjudicator found 70% of contracted work (including extras proven in evidence) had been completed, accepted claimant evidence that $24,602.33 was paid, calculated unpaid contract balance of $3,133.97 and 30% of contract price as $8,320.89, yielding net damages of $5,186.92; claims for defective work and additional extras were dismissed for lack of reliable evidence; costs of $179.35 awarded; judgment entered against Shane Abraham Bennett carrying on business as S. Bennett Construction for $5,366.27.
- Citation
- 2009 NSSM 66
- Parties
- Claimant: Holly Thomas; Claimant: Alan Hughes; Defendant: S. Bennett Construction #863931028; Defendant: Shane Abraham Bennett; Defendant: Christina Anne Bennett
- Court
- Nova Scotia Small Claims Court
- Jurisdiction
- Canada
- Judgment Date
- 4 December 2009
- Procedural Posture
- Small Claims Court Contract/construction / Decision (adjudicator)
- Outcome
- Judgment for claimants in part against Shane Abraham Bennett carrying on business as S. Bennett Construction
- Legal Topics
- Breach of Contract, Expectation Damages, Contract Variations/extras, Completion of Work, Costs, Liability of Sole Proprietor
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Holly Thomas
Claimant
Alan Hughes
Claimant
S. Bennett Construction #863931028
Defendant
Shane Abraham Bennett
Defendant
Christina Anne Bennett
Defendant
Procedural Posture
Small Claims Court Contract/construction / Decision (adjudicator)
Legal Issues
- 1 Whether extras beyond those testified were agreed and payable
- 2 Extent of completion of contracted work and appropriate measure of damages
- 3 Whether performed work was defective/negligent
Ratio Decidendi
On the balance of probabilities the adjudicator found 70% of contracted work (including extras proven in evidence) had been completed, accepted claimant evidence that $24,602.33 was paid, calculated unpaid contract balance of $3,133.97 and 30% of contract price as $8,320.89, yielding net damages of $5,186.92; claims for defective work and additional extras were dismissed for lack of reliable evidence; costs of $179.35 awarded; judgment entered against Shane Abraham Bennett carrying on business as S. Bennett Construction for $5,366.27.
Court Disposition
Judgment for claimants in part against Shane Abraham Bennett carrying on business as S. Bennett Construction
Orders
- Judgment in favour of Holly Thomas and Alan Hughes against Shane Abraham Bennett carrying on business as S. Bennett Construction in the amount of $5,186.92
- Costs awarded to Claimants in the amount of $179.35
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment