Peter Kiewit Sons' Co. v. Eakins Construction Ltd.
Because the subcontractor, with full knowledge of the engineer's position and without obtaining rescission, elected to continue performance under protest, its rights are limited to the terms and remedies of the existing subcontract and the main contract's provisions for extras; there was no frustration nor consent to substitute a new contract so quantum meruit recovery is excluded and the appeal is allowed restoring the trial judgment subject to a reference for the 22 piles at pier 10.
- Citation
- [1960] SCR 361
- Parties
- Defendant/appellant (main Contractor): Peter Kiewit Sons' Company of Canada Limited and Raymond International Company Limited (Kiewit-Raymond); Plaintiff/respondent (sub Contractor): Eakins Construction Limited; Defendant (employer/authority): British Columbia Toll Highways & Bridges Authority
- Court
- Supreme Court of Canada
- Jurisdiction
- Canada
- Judgment Date
- 22 February 1960
- Procedural Posture
- Contract (subcontract Dispute; Appeal) / Appeal to the Supreme Court of Canada From the Court of Appeal for British Columbia
- Outcome
- Appeal allowed; judgment of Court of Appeal reversed in part; trial judgment restored; action dismissed except for contractual recovery for 22 piles at pier 10 to be assessed.
- Legal Topics
- Subcontract Interpretation, Engineer’s Directions, Extra Work, Quantum Meruit, Frustration of Contract, Elective Performance, Costs Bullock Order
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Peter Kiewit Sons' Company of Canada Limited and Raymond International Company Limited (Kiewit-Raymond)
Defendant/appellant (main Contractor)
Eakins Construction Limited
Plaintiff/respondent (sub Contractor)
British Columbia Toll Highways & Bridges Authority
Defendant (employer/authority)
Procedural Posture
Contract (subcontract Dispute; Appeal) / Appeal to the Supreme Court of Canada From the Court of Appeal for British Columbia
Legal Issues
- 1 Whether the disputed pile work was within the subcontract or an extra
- 2 Whether the engineer's addendum/change in plans validly altered subcontractor's obligations
- 3 Whether the original subcontract was rescinded and substituted by a new contract by conduct
Ratio Decidendi
Because the subcontractor, with full knowledge of the engineer's position and without obtaining rescission, elected to continue performance under protest, its rights are limited to the terms and remedies of the existing subcontract and the main contract's provisions for extras; there was no frustration nor consent to substitute a new contract so quantum meruit recovery is excluded and the appeal is allowed restoring the trial judgment subject to a reference for the 22 piles at pier 10.
Court Disposition
Appeal allowed; judgment of Court of Appeal reversed in part; trial judgment restored; action dismissed except for contractual recovery for 22 piles at pier 10 to be assessed.
Orders
- Appeal allowed
- Judgment of the Court of Appeal set aside in respect of quantum meruit recovery against appellant
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment