Martin Developments Ltd. v. D'Arcy
The claim was dismissed because the court characterized the project as a fixed-price contract for the original scope and a cost-plus type arrangement for additional work but the claimant failed to produce records segregating fixed-price work from additional work and therefore failed to prove any additional amount owing; burden lay with claimant to prove entitlement.
- Citation
- 2006 NSSM 22
- Parties
- Claimant: Martin Developments Limited; Defendant: Thomas D'Arcy; Defendant: Mildred D'Arcy
- Court
- Nova Scotia Small Claims Court
- Jurisdiction
- Canada
- Judgment Date
- 24 April 2006
- Procedural Posture
- Small Claims Court Contract / Decision
- Outcome
- Claim dismissed; defendants' counterclaim allowed in part
- Legal Topics
- Cost Plus Contract, Fixed Price Contract, Contract Formation, Contract Variation, Objective Test, Burden of Proof, Counterclaim, Quantum Meruit
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Martin Developments Limited
Claimant
Thomas D'Arcy
Defendant
Mildred D'Arcy
Defendant
Procedural Posture
Small Claims Court Contract / Decision
Legal Issues
- 1 Whether the original $40,000 fixed-price contract was replaced or varied into a cost-plus contract
- 2 Whether a new fixed-price contract for approximately $70,000 (or $90,000) was formed
- 3 Whether claimant proved the amount allegedly owing given mixed invoicing and lack of allocation between original and additional work
Ratio Decidendi
The claim was dismissed because the court characterized the project as a fixed-price contract for the original scope and a cost-plus type arrangement for additional work but the claimant failed to produce records segregating fixed-price work from additional work and therefore failed to prove any additional amount owing; burden lay with claimant to prove entitlement.
Court Disposition
Claim dismissed; defendants' counterclaim allowed in part
Orders
- Claim dismissed
- Order Martin Developments Limited pay Thomas and Mildred D'Arcy $285.25
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment