Victoria Harbour Lumber Co. v. Irwin
- Citation
- (1895) 24 SCR 607
- Status
- Judgment
- Jurisdiction
- Canada
- Court
- Supreme Court of Canada
- Decision
- 6 May 1895
- Posture
- Contract Appeal to Supreme Court of Canada / On Appeal From the Court of Appeal for Ontario; Judgment on Appeal
- Language
- English
More details
- Court
- Supreme Court of Canada
- Decision
- 6 May 1895
- Posture
- Contract Appeal to Supreme Court of Canada / On Appeal From the Court of Appeal for Ontario; Judgment on Appeal
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The thirty‑day clause required both delivery by the vendor and payment by the purchaser to be completed within thirty days from the date of the contract; it did not grant the purchaser thirty days after delivery to pay, and where the purchaser accepted a delivery after that thirty‑day period the seller could immediately sue for the price.
Court disposition
Appeal dismissed with costs; judgment of the Court of Appeal for Ontario affirmed.
Orders
- Appeal dismissed with costs
- Judgment of the Court of Appeal for Ontario affirmed
02
Material facts
Parties
Victoria Harbour Lumber Company
Appellant Counsel: Laidlaw Q.C.; BicknellJames M. Irwin
Respondent Counsel: McCarthy Q.C.; EdwardsAmounts and remedies
- Price Per Thousand Feet: CAD 9.5
- Settlement Period Days: 30
- Delivery Window Days: 10
03
Procedural history
Posture
Contract Appeal to Supreme Court of Canada / On Appeal From the Court of Appeal for Ontario; Judgment on Appeal
04
Questions and positions
Legal issues
- 01
Construction of contract clause as to timing of payment
- 02
Whether action for price was prematurely brought
- 03
Effect of acceptance of delivery after contractual delivery period
Party arguments
- Applicant
- The clause providing 'Settlement to be finally made inside of thirty days' gave the purchaser thirty days after completion of delivery to pay; delivery completed July 1, 1893, so action commenced July 12, 1893 was premature.
- Respondent
- The thirty day clause fixed the mutual obligation to complete delivery and payment within thirty days from the date of the contract; it did not grant the purchaser additional time after delivery; where purchaser accepted a late delivery the seller could bring action immediately for the price.
05
Court’s reasoning
Legal principles
- 01
Judgment of Gwynne J., Victoria Harbour Lumber Co. v. Irwin (1895) 24 SCR 607
Contractual terms must be construed as a whole; time clauses fix the period for mutual performance when so expressed
- 02
Judgment of Gwynne J., Victoria Harbour Lumber Co. v. Irwin (1895) 24 SCR 607
Acceptance of a late delivery (an event not provided for in the contract) does not automatically create a new gratuitous extension of payment time for the purchaser
- 03
Judgment of Gwynne J., Victoria Harbour Lumber Co. v. Irwin (1895) 24 SCR 607
Where a contract prescribes delivery and payment within a fixed period, failure to provide for late performance leaves the innocent party free to sue on acceptance
06
Ratio, limits and disposition
Ratio decidendi
The thirty‑day clause required both delivery by the vendor and payment by the purchaser to be completed within thirty days from the date of the contract; it did not grant the purchaser thirty days after delivery to pay, and where the purchaser accepted a delivery after that thirty‑day period the seller could immediately sue for the price.
Obiter and limits
- If non‑delivery within the thirty days was caused by the vendor, the purchaser would have an action for breach of contract.
- The contract made no provision for delivery or payment following acceptance after the stipulated thirty‑day period, and it would be unreasonable to imply a post‑delivery grace period for payment.
Court disposition
Appeal dismissed with costs; judgment of the Court of Appeal for Ontario affirmed.
- Appeal dismissed with costs
- Judgment of the Court of Appeal for Ontario affirmed
Source and reliance status
Supreme Court of Canada · 6 May 1895
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Supreme Court of Canada
Judgment· 6 May 1895
Victoria Harbour Lumber Co. v. Irwin Collection Supreme Court Judgments Date 1895-05-06 Report (1895) 24 SCR 607 Judges Strong, Samuel Henry; King, George Edwin; Gwynne, John Wellington; Taschereau, Henri-Elzéar; Sedgewick, Robert On appeal from Ontario Subjects Contract Decision Content Supreme Court of Canada The Victoria Harbour Lumber Company v. Irwin (1895) 24 SCR 607 Date: 1895-05-06 The Victoria Harbour Lumber Company (Defendants) Appellants and James M. Irwin (Plaintiff) Respondent 1895: Mar 27, 28; 1895: May 6. Present:—Sir Henry Strong C.J., and Taschereau, Gwynne Sedgewick and King JJ. ON APPEAL FROM THE COURT OF APPEAL FOR ONTARIO. Contract—Sale of timber—Delivery—Time for payment—Premature action. By agreement in writing I. agreed to sell and the V. H. L. Co. to purchase timber to be delivered “free of charge where they now lie within ten days from the time the ice is advised as clear out of the harbour so that the timber may be counted * * * Settlement to be finally made inside of thirty days in cash less 2 per cent for the dimension timber which is at John’s Island.” Held, affirming the decision of the Court of Appeal, that the last clause did not give the purchaser thirty days after delivery for payment; that it provided for delivery by vendor and payment by purchasers within thirty days from the date of the contract; and that if purchasers accepted the timber
after the expiration of thirty days from such date, an event not provided for in the contract, an action for the price could be brought immediately after the acceptance. APPEAL from a decision of the Court of Appeal for Ontario, affirming the judgment of the Divisional Court in favour of the plaintiff. The only question raised on this appeal was whether or not the plaintiff’s action was premature and that question depended on the construction to be placed on the following agreement between the parties. “Memorandum of agreement, in duplicate, entered into this second day of May, 1883.” “Between James M. Irwin, of the town of Peterborough, of the first part, and” “The Victoria Harbour Lumber Company, of the city of Toronto, of the second part.” “The party of the first part sells and the parties of the second part purchase the following dimension timber, as per schedule annexed, now lying at John’s Island in care of Henry Colclough, to be delivered by the party of the first part to the parties of the second part free of charge where they now lie within ten (10) days from the time the ice is advised as clear out of the harbour, so that the timber may be counted, at a price of nine dollars and fifty cents ($9.50) per thousand feet in accordance with the schedule hereto attached, which purports to be a condensed specification of Mr. Cochrane’s measurement of the same, who scaled the
timber and whose scale is accepted between the parties.” “Settlement to be finally made inside of thirty (30) days in cash less 2 per cent for the dimension timber which is at John’s Island.” The defendant company contended that the second clause of this agreement meant that payment was not to be made until thirty days after the delivery was completed and it not having been completed until July 1st, 1893, the action which was commenced on July 12th, 1893, was premature. The trial judge agreed with this contention and dismissed the action. His decision was reversed by the Chancery Division, whose judgment was affirmed by the Court of Appeal. Laidlaw Q.C. and Bicknell for the appellants. McCarthy Q.C. and Edwards for the respondent. The judgment of the court was delivered by: GWYNNE J.—The sole question upon this appeal is whether or not the plaintiff’s action was prematurely brought. I concur in the argument of the learned counsel for the appellants that nothing was by the contract made payable for the timber expressed to be lying at John’s Island until delivery thereof. The true construction of the first paragraph of the contract if it had stood alone was, as I think, that the appellants undertook to pay $9.50 per thousand feet of that timber delivered free of charge, but in that contract if it had so stood no time was fixed for the delivery of the timber further than that it
was agreed that it should take place “within ten days from the time the ice is advised ( as clear out of the harbour,” the second paragraph was therefore inserted in the contract which provides that, “settlement to be finally made inside of 30 days in cash less 2 per cent for dimension timber which is at John’s Island.” This is the paragraph which was relied upon as giving to the appellants 30 days of grace for payment of the price after delivery of the timber, but it does nothing of the kind; what the paragraph was introduced for was manifestly to define more precisely the time for delivery of the timber than by the expression “within ten days from the time the ice is advised as clear of the harbour,” and it expresses the mutual agreement of both parties to the contract, namely, that everything necessary to a final settlement of the contract by both parties, namely-, delivery by the one and payment by the other, shall be made inside of 30 days from the date of the contract. For delivery after that date, and consequently for payment in the event of delivery after that date, the contract makes no provision. If the non-delivery within the 30 days was by reason of the respondent’s default the appellants had their action for breach of contract; but having accepted a delivery of the timber after the expiration of the 30 days named in the contract within which it was to be delivered,
for which event the contract made no provision, it is preposterous to hold that the appellants had by the contract 30 days after delivery, after the expiration of the time named in the contract for delivery, for payment of the price of the timber delivery of which was so accepted. For such an event it is plain that the contract made Ho provision, so no question as to the action having been premature within the terms of the contract could arise. The appeal mast be dismissed with costs. Appeal dismissed with costs. Solicitors for the appellants: Laidlaw, Kappele & Bicknell. Solicitors for the respondent: Edwards & Murray.