Readie Construction Ltd v Geo Quarries Ltd [2021] EWHC 3030 (QB) (12 November 2021)

Readie Construction Ltd v Geo Quarries Ltd [2021] EWHC 3030 (QB) (12 November 2021)

Clause 4.1 of the contract, requiring payment in full without deduction or withholding whatsoever on any account, is effective to exclude the defence of abatement for defective goods. Once there has been bona fide, purported delivery under the contract, the obligation to pay arises, and the buyer cannot withhold...

Source-derived case information.

Citation
[2021] EWHC 3030
Parties
Appellant/defendant: Readie Construction Limited; Respondent/claimant: Geo Quarries Limited
Jurisdiction
England and Wales
Judgment Date
12 November 2021
Procedural Posture
Appeal (civil, Commercial) / Appeal From Summary Judgment (county Court) to High Court
Outcome
Appeal dismissed
Legal Topics
Abatement, Exclusion of Abatement, Retention of Title, Summary Judgment, Section 49 Sale of Goods Act 1979, Interpretation of Payment Clauses, Pay Now Argue Later Clauses
Commercial Law Contract Law Sale of Goods Abatement Exclusion of Abatement Retention of Title Summary Judgment Section 49 Sale of Goods Act 1979 +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 14 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Readie Construction Limited

Appellant/defendant

Geo Quarries Limited

Respondent/claimant

Procedural Posture

Appeal (civil, Commercial) / Appeal From Summary Judgment (county Court) to High Court

  1. 1 Whether clause 4.1 of the contract excludes the defence of abatement for defective goods
  2. 2 Whether the contract permits Geo to claim the price under section 49(2) of the Sale of Goods Act 1979

Ratio Decidendi

Clause 4.1 of the contract, requiring payment in full without deduction or withholding whatsoever on any account, is effective to exclude the defence of abatement for defective goods. Once there has been bona fide, purported delivery under the contract, the obligation to pay arises, and the buyer cannot withhold payment on the basis of alleged defects. The payment clause also satisfies section 49(2) of the Sale of Goods Act 1979, as payment is due on a day certain irrespective of delivery, entitling the seller to claim the price even though property has not passed due to the retention of title clause.

Court Disposition

Appeal dismissed

Orders

  • Summary judgment in favour of Geo Quarries Limited for £224,091.52 is upheld.
  • Readie Construction Limited is to pay the sum claimed plus any applicable interest and costs.