Fitzpatrick Contractors Ltd v Tyco Fire & Integrated Solutions (UK) Ltd
The trial cannot proceed on 10th November 2008 because the timetable is unachievable given the outstanding steps, the state of witness and expert evidence preparation, and the practical difficulties of the compressed schedule. The primary responsibility for the delay lies with Fitzpatrick, but Tyco's amended pleadings also contributed. The overriding objective and fairness require adjournment.
- Parties
- Applicant/claimant: Fitzpatrick Contractors Limited; Respondent/defendant: Tyco Fire and Integrated Solutions (UK) Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 25 July 2008
- Procedural Posture
- Civil (construction Dispute) / Application to Adjourn Trial
- Outcome
- Application to adjourn trial granted; costs order made against applicant
- Legal Topics
- Adjournment of Trial, Case Management, Costs Orders, Expert Evidence, Delay in Proceedings
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Fitzpatrick Contractors Limited
Applicant/claimant
Tyco Fire and Integrated Solutions (UK) Limited
Respondent/defendant
Procedural Posture
Civil (construction Dispute) / Application to Adjourn Trial
Legal Issues
- 1 Whether the trial scheduled for 10th November 2008 should be adjourned
- 2 Whether the parties can be ready for trial in accordance with the overriding objective
- 3 Responsibility for delays and costs occasioned by the adjournment
Ratio Decidendi
The trial cannot proceed on 10th November 2008 because the timetable is unachievable given the outstanding steps, the state of witness and expert evidence preparation, and the practical difficulties of the compressed schedule. The primary responsibility for the delay lies with Fitzpatrick, but Tyco's amended pleadings also contributed. The overriding objective and fairness require adjournment.
Court Disposition
Application to adjourn trial granted; costs order made against applicant
Orders
- Trial adjourned from 10th November 2008 to 21st April 2009
- Fitzpatrick Contractors Limited to pay 60% of Tyco Fire and Integrated Solutions (UK) Limited's costs of and occasioned by the adjournment, including costs of the application hearing
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment