Sleaford Building Services Ltd v Isoplus Piping Systems Ltd [2023] EWHC 969 (TCC) (28 April 2023)
The Part 8 claim was unsuitable for summary determination due to lack of particularisation, potential factual disputes (including waiver), and the need for further evidence on the operation and breach of clause 21.4. Accordingly, the adjudicator's decision is enforceable and judgment is entered for Isoplus. The Part 8 claim is dismissed.
- Citation
- [2023] EWHC 969 (TCC)
- Parties
- Part 8 Claimant / Part 7 Defendant: Sleaford Building Services Limited; Part 8 Defendant / Part 7 Claimant: Isoplus Piping Systems Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 28 April 2023
- Procedural Posture
- Consolidated Part 7 (adjudication Enforcement) and Part 8 (declaratory Relief) Proceedings / Judgment After Hearing on Enforcement and Declaratory Relief
- Outcome
- Judgment for Isoplus on the Part 7 claim; Part 8 claim dismissed.
- Legal Topics
- Adjudication Enforcement, Conditions Precedent to Payment, Waiver, Declaratory Relief, Interpretation of Construction Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sleaford Building Services Limited
Part 8 Claimant / Part 7 Defendant
Isoplus Piping Systems Limited
Part 8 Defendant / Part 7 Claimant
Procedural Posture
Consolidated Part 7 (adjudication Enforcement) and Part 8 (declaratory Relief) Proceedings / Judgment After Hearing on Enforcement and Declaratory Relief
Legal Issues
- 1 Whether clause 21.4 of the subcontract is a condition precedent to payment and if so, whether Isoplus complied with it
- 2 Whether Sleaford's Part 8 claim for declaratory relief is suitable for determination under Part 8 procedure
- 3 Whether the adjudicator's decision should be enforced
Ratio Decidendi
The Part 8 claim was unsuitable for summary determination due to lack of particularisation, potential factual disputes (including waiver), and the need for further evidence on the operation and breach of clause 21.4. Accordingly, the adjudicator's decision is enforceable and judgment is entered for Isoplus. The Part 8 claim is dismissed.
Court Disposition
Judgment for Isoplus on the Part 7 claim; Part 8 claim dismissed.
Orders
- Judgment for Isoplus in the sum of £323,502.32 plus interest.
- Part 8 claim by Sleaford dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment