Henry Construction Projects Ltd v ProMEP Ltd [2024] EWHC 1825 (TCC) (16 July 2024)
The CVA expressly excluded ProMep's claims against Henry from its scope by clear wording in clause 8.3, so those claims survived the CVA and were enforceable. There was no automatic insolvency set-off applicable to these claims under the CVA. The summary of counsel's advice provided by ProMep did not amount to a material misrepresentation or fraud capable of vitiating the adjudicator's decision. The adjudicator's decision was therefore enforceable by summary judgment.
- Citation
- [2024] EWHC 1825 (TCC)
- Parties
- Claimant (part 7 Defendant, Part 8 Claimant): Henry Construction Projects Limited; Defendant (part 7 Claimant, Part 8 Defendant): ProMEP Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 16 July 2024
- Procedural Posture
- TCC (technology and Construction Court) Part 7 and Part 8 Claims / Judgment on Summary Judgment Application for Enforcement of Adjudicator's Decision and Related Declaratory Relief
- Outcome
- Summary judgment granted for ProMep; adjudicator's decision enforced.
- Legal Topics
- Adjudication Enforcement, Company Voluntary Arrangement (cva), Insolvency Set Off, Contract Interpretation, Fraud in Adjudication, Summary Judgment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Henry Construction Projects Limited
Claimant (part 7 Defendant, Part 8 Claimant)
ProMEP Limited
Defendant (part 7 Claimant, Part 8 Defendant)
Procedural Posture
TCC (technology and Construction Court) Part 7 and Part 8 Claims / Judgment on Summary Judgment Application for Enforcement of Adjudicator's Decision and Related Declaratory Relief
Legal Issues
- 1 Whether ProMep's claims against Henry were excluded from the CVA and thus enforceable post-CVA
- 2 Whether insolvency set-off under IR 14.25 applied to the claims between the parties under the CVA
- 3 Whether ProMep's summary of counsel's advice constituted a material misrepresentation amounting to fraud and thus a defence to enforcement of the adjudicator's decision
Ratio Decidendi
The CVA expressly excluded ProMep's claims against Henry from its scope by clear wording in clause 8.3, so those claims survived the CVA and were enforceable. There was no automatic insolvency set-off applicable to these claims under the CVA. The summary of counsel's advice provided by ProMep did not amount to a material misrepresentation or fraud capable of vitiating the adjudicator's decision. The adjudicator's decision was therefore enforceable by summary judgment.
Court Disposition
Summary judgment granted for ProMep; adjudicator's decision enforced.
Orders
- Henry Construction Projects Limited to pay ProMep Limited the sum awarded by the adjudicator (£90,380.49).
- Henry's application for specific disclosure of counsel's advice refused.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment