R J Knapman Ltd. v Richards & Ors
The adjudicator’s decision did not amount to a comprehensive determination of all delay issues or entitlement to further liquidated damages, nor did it operate as a clause 2.6 certificate under the contract. Therefore, the defendants are not entitled to set-off further liquidated damages against the adjudicator’s award, and the claimant is entitled to enforce the monetary award notwithstanding any ongoing disputes about other aspects of the adjudicator’s decision.
- Parties
- Claimant: R J Knapman Limited; Defendants: Richards and Others
- Jurisdiction
- England and Wales
- Judgment Date
- 12 October 2006
- Procedural Posture
- Construction Contract Enforcement / Judgment on Application to Enforce Adjudicator's Decision
- Outcome
- Judgment for the claimant
- Legal Topics
- Adjudication Enforcement, Liquidated Damages, Set Off, Extensions of Time, Appropriation and Reprobation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
R J Knapman Limited
Claimant
Richards and Others
Defendants
Procedural Posture
Construction Contract Enforcement / Judgment on Application to Enforce Adjudicator's Decision
Legal Issues
- 1 Whether the claimant can enforce the monetary part of the adjudicator’s decision while disputing other parts
- 2 Whether the defendants are entitled to set-off further liquidated damages against the adjudicator’s award
Ratio Decidendi
The adjudicator’s decision did not amount to a comprehensive determination of all delay issues or entitlement to further liquidated damages, nor did it operate as a clause 2.6 certificate under the contract. Therefore, the defendants are not entitled to set-off further liquidated damages against the adjudicator’s award, and the claimant is entitled to enforce the monetary award notwithstanding any ongoing disputes about other aspects of the adjudicator’s decision.
Court Disposition
Judgment for the claimant
Orders
- Judgment entered for the claimant in the sum of £19,339.93
- Payment to be made within 14 days together with interest
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment