M Davenport Builders Ltd v Greer & Anor
A defendant subject to an immediate obligation to pay under an adjudicator's decision based on failure to serve a Payment Notice or Pay Less Notice must discharge that obligation before relying on a subsequent 'true value' adjudication; summary judgment is granted to enforce the original adjudication decision.
- Parties
- Claimant: M Davenport Builders Limited; First Defendant: Mr Colin Greer; Second Defendant: Mrs Julia Greer
- Jurisdiction
- England and Wales
- Judgment Date
- 20 February 2019
- Procedural Posture
- Application to Enforce Adjudication Decision / Summary Judgment
- Outcome
- Summary judgment for the Claimant to enforce the adjudication decision.
- Legal Topics
- Adjudication Enforcement, Payment Obligations, Set Off and Counterclaim, Scheme for Construction Contracts, Housing Grants, Construction and Regeneration Act 1996
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
M Davenport Builders Limited
Claimant
Mr Colin Greer
First Defendant
Mrs Julia Greer
Second Defendant
Procedural Posture
Application to Enforce Adjudication Decision / Summary Judgment
Legal Issues
- 1 Whether a defendant can rely on a 'true value' adjudication as a defence to enforcement of an earlier adjudication decision without first paying the sum ordered by the earlier adjudicator
- 2 Whether policy and statutory provisions require payment before commencing or relying on a subsequent adjudication
Ratio Decidendi
A defendant subject to an immediate obligation to pay under an adjudicator's decision based on failure to serve a Payment Notice or Pay Less Notice must discharge that obligation before relying on a subsequent 'true value' adjudication; summary judgment is granted to enforce the original adjudication decision.
Court Disposition
Summary judgment for the Claimant to enforce the adjudication decision.
Orders
- Defendant to pay Claimant £106,160.84 plus interest.
- Defendant to pay Claimant's costs of proceedings, to be assessed if not agreed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment